what will do when 7days concrete has failed and structure has
constructed?
Answer Posted / karnam seenu
,When a cube test conducted for a structural member fails, it is advisable to go immediately for a core cutting test and send the sample slab core to test the compressive strength. You need not wait for 14 days or 28 days.
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is the minimum size of the particles of silt soil?
What year was the keystone power plant in Indiana County constructed?
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
What are your future hopes for this job?
How to calculate the cement plastering for circular and rectangular water storage tanks and how to calculate the area of circular and rectangular floor?? Please help me
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
How many square meter can a worker/labor demolish a structure per day?
What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?
Soil bearing capacity formula
what is BPM in concrete demolition hammers. what is better a higher value or lower
What are the phases inspections are done by local authority while construction?
What is binding spacing of the rebars at lapping zones.
what is the difference between np2 and np3 concrete mix
What are the advantages of cad software?
Howmuch bend to be provide for 200/600 BEEM