what will do when 7days concrete has failed and structure has
constructed?
Answer Posted / suresh bariya
Generally we will wait for 28th day test,if 28 days test
result get failed then immidiate inform your structural
consultant,consultant will suggest the rebound hammer test
which is not a perfect solution, then do the core cutting
test it will give you the actual result of that strucutural
concrete, from this result you will know the actual
strength ,it will decide the jacketing will serve the
purpose or brecking is the final solution.
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
what"s the sort of beams?
WHAT THREE SPECFIC JOB POSITIONS TO YOU TARGET FROM THE COMPANY?
Concrete cover for slab, column, beam and footing?
Define What are the materials used in building a gravity dam?
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available
where will be the reinforcement of slab placed when there is an inverted beam and the bottom of the beam and slab are at same level ?
in block masonry l=10',b=0.5',H=10',Calculate cement ,sand and no.Of blocks?
how much area can be platered by a mason for exterior
Tell me about triple point of water.
What do you mean by honeycomb in concrete?
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
What are the techniques to measure road difference?
how to do sudoko puzaals?
why +1 to be followed for calculating the no of bars in BBS. Please explain