what will do when 7days concrete has failed and structure has
constructed?
Answer Posted / suresh bariya
Generally we will wait for 28th day test,if 28 days test
result get failed then immidiate inform your structural
consultant,consultant will suggest the rebound hammer test
which is not a perfect solution, then do the core cutting
test it will give you the actual result of that strucutural
concrete, from this result you will know the actual
strength ,it will decide the jacketing will serve the
purpose or brecking is the final solution.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
how we can find sieve #4 is 4.75mm?
What is difference between engineering stress and true stress?
how i convert mm into standard wire guage (SWG)no.
how to calculate quantity of cement,sand & aggregate for u.c.r / r.r masonry in cm 1:6
Why are the bolts that hold steel rails together in oval holes?
What type of tensile strength is handling by crank in beam? Thanks.
in 100 cft = 1350 bricks in 100 cft = ? bloks
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
how much need cement bags for block work of wall approx 1000 hollow blocks 20x20x40cm
Are cruise ships built for the transatlantic run?
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter
what is civil enginnering & what you need of this course?
How foundation is designed, Column design and beam design
Explain what are the skills required to become an architect?