how to calculate concrete quantity for footing using M25 grade
1:1:2 for 730cft.
Answers were Sorted based on User's Feedback
Answer / kuldeep singh sevariya
dry quantity of 1 cum wet concrete =1.54
730cft=20.67cum of wet quentity
so,dry quentity of 20.67cum=1.54*20.67=31.83cum
CEMENT=(31.83*1)/(1+1+2)=7.96cum
(Density of cement-1440kg/cum)
(7.96*1440)/50=229.176Bags
SAND=(31.83*1)/4=7.92CUM, SO, 1600*7.92=12672 KG
AGGREGATE=(31.83*2)/4=15.92 CUM
SO,1520*15.92=24198.4 KG
Is This Answer Correct ? | 14 Yes | 3 No |
Answer / mohammed aijaz hussain
Volume of Wet concrete = 730 cu.ft. = 20.68 cu.m.
Volume of Dry concrete = 1.75 X 20.68 = 36.19 cu.m.
Volume of cement = 1/4 X 36.19 = 9.048 cu.m.
= 258.5 Bags
Volume of Sand = 1/4 X 36.19 = 9.048 cu.m.
Volume of Aggregate = 2/4 X 36.19 = 18.095 cu.m.
Is This Answer Correct ? | 5 Yes | 2 No |
what are the standard & nominal size of brick
What is specific gravity & how it is calculated
What is the maximum strength of cub compress strength in one cub testing
what discoveries did you have in relation to your course?
could u tell me how to used deform stell bar in reinforce concret?i wanna know the general using in the site!
how much quantity of cement(bags)concrete(20mm)and sand(sqft)is used in 1:3:6 PCC
In earth work 1300 cum soil how to calculate how many liters require in water
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
1)What is swear, swage and storm water? 2)What are the sizes of bricks based on Nominal, practical and standard? 3) What is the distinguies between the grade of cement 43, 53?
Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
16 Answers Reliance, Siddhi Constructions,
how to take concrete quantity for precast segment for viaduct project?
what means if slump is less than 25mm and greater than 80mm?