how to calculate concrete quantity for footing using M25 grade
1:1:2 for 730cft.
Answer Posted / mohammed aijaz hussain
Volume of Wet concrete = 730 cu.ft. = 20.68 cu.m.
Volume of Dry concrete = 1.75 X 20.68 = 36.19 cu.m.
Volume of cement = 1/4 X 36.19 = 9.048 cu.m.
= 258.5 Bags
Volume of Sand = 1/4 X 36.19 = 9.048 cu.m.
Volume of Aggregate = 2/4 X 36.19 = 18.095 cu.m.
| Is This Answer Correct ? | 5 Yes | 2 No |
Post New Answer View All Answers
For Wet Mix Mecadam design what is Optimum moisture content
What is reinforced concrete?
In Abutment walls (A1 side) why we are adopting fixed bearing (POT-PTFE)?
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
Explain the importance of moment of inertia?
In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?
how can i calculate cement in brickwork
In reclamation works what are the importance of geotextiles and sand?
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
Explain what is the difference between built area and super built up area?
How do you determine specific gravity of cement?
The concrete slump recommended for beams and slabs; is?
how can we calculate steel value, depending on load