how to calculate concrete quantity for footing using M25 grade
1:1:2 for 730cft.
Answer Posted / mohammed aijaz hussain
Volume of Wet concrete = 730 cu.ft. = 20.68 cu.m.
Volume of Dry concrete = 1.75 X 20.68 = 36.19 cu.m.
Volume of cement = 1/4 X 36.19 = 9.048 cu.m.
= 258.5 Bags
Volume of Sand = 1/4 X 36.19 = 9.048 cu.m.
Volume of Aggregate = 2/4 X 36.19 = 18.095 cu.m.
| Is This Answer Correct ? | 5 Yes | 2 No |
Post New Answer View All Answers
In cement making,what is meaning of blend,fineness,density.
Coverage of 25mm.thick ratio of 1:4 cement mortar?
How to do base isolation using ETABS software?
Pls provide me with the calculation or codes related to de- shuttering of flat slabs
can you provide a link for manual design of building?
What are the different methods for drawing an arc?
what is meant by shear center?????
why development length = 50D . why not 100D
What is quantity of cement and sand required for 2000sqft of tiling?
if dia of inner circle is 42 m and depth is 1.5 m and width is 1 m ,then whait is the quantity of steel?
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
What type of tensile strength is handling by crank in beam? Thanks.
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
what is a well