how to calculate concrete quantity for footing using M25 grade
1:1:2 for 730cft.

Answer Posted / mohammed aijaz hussain

Volume of Wet concrete = 730 cu.ft. = 20.68 cu.m.

Volume of Dry concrete = 1.75 X 20.68 = 36.19 cu.m.

Volume of cement = 1/4 X 36.19 = 9.048 cu.m.
= 258.5 Bags

Volume of Sand = 1/4 X 36.19 = 9.048 cu.m.

Volume of Aggregate = 2/4 X 36.19 = 18.095 cu.m.

Is This Answer Correct ?    5 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is concrete canvas?

1778


Define What is a kip?

732


What is the difference between routing maintenance and major maintenance in school facilities?

670


What is the name of this multiplication factors ?

1713


Is there any course for billing available in Mumbai? If yes then please mail me the details..

1818






what are the code used for residental building?

2054


how to identify np3 pipe and np4 pipe

1536


Civil engineering related

1522


In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.

3721


I want to join bhel because

1775


How to calculate quantity of cement , sand and granite from concrete mix ratio and volume of work

3154


What is difference between code and standard and specification?

1810


What is the value of live load that should be incorporated in design of locker room and cash vault room while designing a building for commercial bank?

2240


What do you mean by bond? What are the different types of bonds?

1662


what is the calculation of raw material for 0.35cum of m-15

1048