how to calculate concrete quantity for footing using M25 grade
1:1:2 for 730cft.
Answer Posted / mohammed aijaz hussain
Volume of Wet concrete = 730 cu.ft. = 20.68 cu.m.
Volume of Dry concrete = 1.75 X 20.68 = 36.19 cu.m.
Volume of cement = 1/4 X 36.19 = 9.048 cu.m.
= 258.5 Bags
Volume of Sand = 1/4 X 36.19 = 9.048 cu.m.
Volume of Aggregate = 2/4 X 36.19 = 18.095 cu.m.
Is This Answer Correct ? | 5 Yes | 2 No |
Post New Answer View All Answers
what is concrete canvas?
Define What is a kip?
What is the difference between routing maintenance and major maintenance in school facilities?
What is the name of this multiplication factors ?
Is there any course for billing available in Mumbai? If yes then please mail me the details..
what are the code used for residental building?
how to identify np3 pipe and np4 pipe
Civil engineering related
In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
I want to join bhel because
How to calculate quantity of cement , sand and granite from concrete mix ratio and volume of work
What is difference between code and standard and specification?
What is the value of live load that should be incorporated in design of locker room and cash vault room while designing a building for commercial bank?
What do you mean by bond? What are the different types of bonds?
what is the calculation of raw material for 0.35cum of m-15