what is the allowable silt % in river sand for Dam
concreting.
Answers were Sorted based on User's Feedback
Answer / pradeep k sharma
AS PER IS CODE, IT IS 3% ,BUT CONSIDERING THE COMPULSION TO
USE THE AVAILABLE RIVER SAND IN THE NEAR BY, THIS LIMIT CAN
BE INCREASED UP TO 5% ,IF ADVERSE EFFECT IS NOT OBSERVED ON
THE STRENGTH OF CONCRET CUBES TESTED BY CONDUCTING TRIAL
MIX TEST IN LABORATORY,IT IS UP TO THE DESCRETION OF
ENGINEER IN-CHARGE TO AMEND THE LIMITS GIVING DUE WEIGHTAGE
TO ALL THE FACTORS AS MENTIONED.
Is This Answer Correct ? | 5 Yes | 0 No |
how to calculate cost for MS plate shuttering (show calculation/assumptions)
How to marking the building
why shear is not considered in limit state of serviceability??
1)pile is of 200mm dia.-- a)tell the cutting length of ring considering 2cm cover b) tell the quantity of concrete considering pile length as 3m c) tell concrete quantity in bulb
What is the per square fee cost of external development of a multistorey group housing project
how to calculate shuttering design & position & quantity of props & type of method for succsessful work
What is the strength of 1:6:12 mix?
How much cement will require for 1Rmt Skirting laying
Required concret Surface Temperature prior to coating of epoxy pain with references ASTM or ACI whatever
How to convert and use 10mm dia steel 150mm spacing instead of 12mm dia steel which is spacing?
Why we are using 150 mm X 150 mm X 150 mm cubes for testing the compressive strength of concrete in CTM and why not other sizes?
How much quantity of rod binding work by a rod binder per day