If do cube Test for 28 Days,when shall can do testing? after completion of 28 days it means 29th day or 28th day which one correct?
Answers were Sorted based on User's Feedback
Answer / cherry
we have to calculate the date that the next day of cube catsting is.29th day
Is This Answer Correct ? | 0 Yes | 2 No |
explain how to calculate top and bottom diagonals for transimission line tower foundation with prop setting
what is the allowable silt content in concrete?
how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing
For making a new road in a village having a school & hospital , tell the steps of construction systemically ?
0 Answers UPSSSC Uttar Pradesh Subordinate Services Selection Commission,
reinforcement lapping for short pile and long pile
Can we use PPC cement for RCC works? Upto which grade it can be used?
The definition of national highway
whatare the load combinations which are used for the foundation design in a tall structure ( 10 storied building)?
concrete mix design for M 30 Grade
a revised estimate is prepared when the original estimate has exceed by more than 1 percent 2 10 18.40
what is a well
material requred for 1 square foot lanter with formula