Difference between MCC and PDB
Answers were Sorted based on User's Feedback
Answer / benedict
MCC Means Motor control center,PDB Means Power Distribution Board.
Is This Answer Correct ? | 31 Yes | 1 No |
MCC:
The MCC means Motor control center. in this MCC
connects the Motors.
PDB:
The PDB means Power distribution board. In this PDB
connects only the feeders(power supply feeders)... i.e the
distribution board means to distribute the powers only...
Is This Answer Correct ? | 22 Yes | 1 No |
Is it required to use 2 nos of body earthings to any machine though if we use TP with E supply is provided to Machine?
why need of ac exietation in alternater.
how to test power transformer.YNd11
how rating of transformer is selected for any new plant/what kind of load is cosidered/what kind of fadtors are considered/ pz give standard procedure
If 3-Ph motor of same rating connected in Delta & Star for same load one by one then which connection take more current in running (not in starting)for full load.(eg 8.5 KW,3-Ph 400 V)
why we increase the small speed of turbine when alternator just synchronized to grid in steam power plant
IC 741 is opampIC..moreover AND OR NOT ICs also have '74' in them.. why is that number specifically used?
Sir, plz tell me the relation b/w KW and frequency in Variable frequency Drive?
when we connect the capacitor banks in series with the circuit?
what is the function of commutator in dc motor?
Explain Analog and Digital signals?