How do you derive the quantity of cement & sand in brick work
construction in 1Meter cube, using CM 1:6 and bricks of size
19*9*9 cm
Answers were Sorted based on User's Feedback
Answer / sag
Volume of bricks with mortar=.2*.1*.1=.002
No of bricks=1/.002=500
Volm of 500 bricks=.19*.1*.1=.7695
Volume of mortar=1-.7695=.2305
Add 15% for wastage and 30% for dry mortar
Now volume of plaster=.2305+.2305*.15+.2305*.3=.334
1:6 cement and sand 1+6=7
Volume of cement=1/7*.334=.048m3=1.36 beg
Volume of sand= .048*6=.288m3
| Is This Answer Correct ? | 33 Yes | 5 No |
Answer / mandeep thakur
By this Formula we can Work out roughly, But Not 100%
Correct
0.3*28.8/sum of Ratio e.g(1:4 is equal 1+4=5
than .3*28.8/5 Only For brick Work.
| Is This Answer Correct ? | 9 Yes | 5 No |
Answer / prakash
3/1+6=0.42 cum cement and 2.57cum sand required ,brick for 1
cm is 500 nos
| Is This Answer Correct ? | 2 Yes | 3 No |
Answer / saif raza
1# Brick required :- 650 nos
2# Cement :- 1.23 bags
3# Sand :- 0.25 cum
| Is This Answer Correct ? | 4 Yes | 8 No |
What is the consumption of Brick in one meter cube both 6inch & 4inch thick
i have a bar of 20 and 16, lap length is 48*dia of bar, what is the lap length here
how to find out spacing inbetween bars instead of 8dia 100c/c to 10dia bars
How much cement & coarse sand is used in 1 Sqm plaster for ratio 1:4 of thickness 20 mm ?
the shearing strength of cohesionless soil depends on
In case of a beam ,main steel is provided along the longer span because, bending moment is directly proportional to length but why in case of one way slab main steel is provided along shorter span while as bending takes place along longer span?comment
What the approval that owner will give to contractor during construction project period? What will the affect on project if delays due approvals?
what"s the formula to find the quantity (consumption) of cement,sand,aggregate for 1m3(1:2:4)?
11 Answers ABB, Construction, Isher, L&T, Saudi Oger, Spectra, Strati,
What is the pet difference between bent up bar and cranked bar ?
1 Answers Foundation Stone, GHH,
What are the benefits of rcc pipes over steel designed pipes?
Coarse aggregate & fine aggregates are called inert material when used in RCC work because------
What are the applications of cad?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)