How do you derive the quantity of cement & sand in brick work
construction in 1Meter cube, using CM 1:6 and bricks of size
19*9*9 cm
Answers were Sorted based on User's Feedback
Answer / sag
Volume of bricks with mortar=.2*.1*.1=.002
No of bricks=1/.002=500
Volm of 500 bricks=.19*.1*.1=.7695
Volume of mortar=1-.7695=.2305
Add 15% for wastage and 30% for dry mortar
Now volume of plaster=.2305+.2305*.15+.2305*.3=.334
1:6 cement and sand 1+6=7
Volume of cement=1/7*.334=.048m3=1.36 beg
Volume of sand= .048*6=.288m3
Is This Answer Correct ? | 33 Yes | 5 No |
Answer / mandeep thakur
By this Formula we can Work out roughly, But Not 100%
Correct
0.3*28.8/sum of Ratio e.g(1:4 is equal 1+4=5
than .3*28.8/5 Only For brick Work.
Is This Answer Correct ? | 9 Yes | 5 No |
Answer / prakash
3/1+6=0.42 cum cement and 2.57cum sand required ,brick for 1
cm is 500 nos
Is This Answer Correct ? | 2 Yes | 3 No |
Answer / saif raza
1# Brick required :- 650 nos
2# Cement :- 1.23 bags
3# Sand :- 0.25 cum
Is This Answer Correct ? | 4 Yes | 8 No |
What is standard sand? What is coarse & fine sand? What is foundation? What is the seze of hooks in various Reinforced section? What is the formula of providing clear cover? What is the basic diff. between working stress & Limit state design? What is &cbc and fck? what are the primary & secondary test of water purification?
Prop carrying load capacity
How to build the floor to ceiling bookcase?
How to rectify thermal cracks (2mm wide, 9mm deep aprx. ) developed in tremix finished concrete floor?
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).
what is the minimum spacing required for slab & beam reinforcement
How many cement bags of 50Kgs will be required for 2600sqft terrace with thickness of 5".
Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.
WILL ANY COLLEAGUE TELL ME THAT WATER RATIO IS FIXED FOR ANY TYPE OF CONCRETE? OR HOW CAN WE DETERMINE THE RATIO OF WATER IN A CONCRETE MIX.
calculate for 1 m3 cement, sand, coarse agree gate ,kg?
what is DLC
What is Rankine Cycle?