How do you derive the quantity of cement & sand in brick work
construction in 1Meter cube, using CM 1:6 and bricks of size
19*9*9 cm
Answer Posted / prakash
3/1+6=0.42 cum cement and 2.57cum sand required ,brick for 1
cm is 500 nos
| Is This Answer Correct ? | 2 Yes | 3 No |
Post New Answer View All Answers
Discuss some applications of modular elasticity?
What is the crank length in the slab?
Why we provide hair pin for shed
how to determine H- zone in a column? where it will occur?
What are the applications of cad?
How many types of slabs are there & how to design it?
How many axes do cartesian coordinate system has?
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
silt%= silt volume/ silt+sand volume is this right?
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
What is componsation
How to take labor charges for construction of 1cum of concrete?
HOw much % of premium on DSR-2013 currently
Which tests are performed on soil to decide the type of foundation to be provided.
What is modular elasticity?