how many no of cement bags required for 1:4 plastering for
100 sqft?
how many no of cement bags required for 1:3 plastering for
ceiling for 100 sqft?
Answers were Sorted based on User's Feedback
Answer / eng.mehboobullah
for calculating the volume of cement in this question it
also need thickess. we consider the thickness of the
plaster 0.5 inch = 0.04' thus the total volume will be 4cft.
this is the wet volume now multiplying it with constant
1.27 the dry volume will be 5.08
now sum of ratio is 5 according to the formula
1 x 5.08/5 = 1.01 cft one cement bag have volume
of 1.25 cft now dividing it on 1.25 we get
1.01/1.25 = 0.81 bags
in plaster the volume of cement depends on the thickness of
the plaster but normally it is adopted as 1/2" that is the
answer of both question change the thickness of the plaster
will change the value of volume of cement. thanks
| Is This Answer Correct ? | 97 Yes | 28 No |
Answer / aijaz hussain, modi builders
For plastering ceiling, thickness will be 10 mm in CM (1:3)
To cover an area of 100 sft. plastering 50 kgs is required
And for plastering the walls in CM (1:4), quantity of
cement required to cover 100 sft. 20 mm thickness will be
85 kgs.
| Is This Answer Correct ? | 36 Yes | 19 No |
Answer / pramod rajput
1:4 12mm thk 1beg/10 m2 and 1:3 12mm thk 1.35begs/10 m2 1 sqmtr=10.76 sqft
| Is This Answer Correct ? | 21 Yes | 10 No |
Answer / ahmed j
Thikness of plaster for 1st coat is roush 12mm (1.6)(1.5)(1.4)
Thikness of plaster for 2nd coat is fine 8mm (1.4)(1.3)
Area is 100sft/3.28^2=0.92
.92*.012=0.011
Sand 1cum required is 1.25cum
1.25/4=0.3125
0.01104*.3125*1440=50.19 Kgs Cement
(1.3)
Area = .92mtr sqr *.008(fine)=.0736*0.21=.0156*1440=22.48 Kgs Cement
| Is This Answer Correct ? | 11 Yes | 6 No |
Answer / prashanth kumar
MATERIAL REQUIRED FOR PLASTERING 100 SQUARE FEET OF CEILING WITH 12MM THICKNESS IN CM(1:3) IS 1.2 BAGS OF CEMENT AND IN CM(1:4) IS 1 BAG OF CEMENT
| Is This Answer Correct ? | 8 Yes | 3 No |
Answer / lawrence.m
We assume the thickness is approx. 0.5inch. So that the volume is 100sqftx0.5=50cft(1.416cum).
For 1 cum( CM1:4), 1/5x 1440= 288Kg cement required.
Therefore, 1.416cum = 407 Kg required(Approx 8 bags)
For CM 1:3, = 510 Kg (Approx. 10 bags)
| Is This Answer Correct ? | 10 Yes | 58 No |
how much difference we have to provide when column steel staggered
in design case of structural member best suitrable percentage of steel limit is what
what is bitumen emultion where it is use
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
1)What is the maximum size of aggregate that can be used for M-50 grade concrete ? Code teh authority?
Are you ready to relocate with your immediate family to United States as a new employee?
what is mean by k150
How to convert n/mm2 in to kg/cm2?
38 Answers Rvr Projects Pvt Ltd, Soma Enterprises, Unitech, Wipro,
Define What is passive earth pressure ?
What are the defects in concrete?
3. What are the disadvantages of your present job, things you do not like about it?
How to calculate the cement consumption in RR Masonry in CM 1:8 for the foundation of Ground Level Reservoir
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)