how many no of cement bags required for 1:4 plastering for
100 sqft?
how many no of cement bags required for 1:3 plastering for
ceiling for 100 sqft?
Answers were Sorted based on User's Feedback
Answer / eng.mehboobullah
for calculating the volume of cement in this question it
also need thickess. we consider the thickness of the
plaster 0.5 inch = 0.04' thus the total volume will be 4cft.
this is the wet volume now multiplying it with constant
1.27 the dry volume will be 5.08
now sum of ratio is 5 according to the formula
1 x 5.08/5 = 1.01 cft one cement bag have volume
of 1.25 cft now dividing it on 1.25 we get
1.01/1.25 = 0.81 bags
in plaster the volume of cement depends on the thickness of
the plaster but normally it is adopted as 1/2" that is the
answer of both question change the thickness of the plaster
will change the value of volume of cement. thanks
| Is This Answer Correct ? | 97 Yes | 28 No |
Answer / aijaz hussain, modi builders
For plastering ceiling, thickness will be 10 mm in CM (1:3)
To cover an area of 100 sft. plastering 50 kgs is required
And for plastering the walls in CM (1:4), quantity of
cement required to cover 100 sft. 20 mm thickness will be
85 kgs.
| Is This Answer Correct ? | 36 Yes | 19 No |
Answer / pramod rajput
1:4 12mm thk 1beg/10 m2 and 1:3 12mm thk 1.35begs/10 m2 1 sqmtr=10.76 sqft
| Is This Answer Correct ? | 21 Yes | 10 No |
Answer / ahmed j
Thikness of plaster for 1st coat is roush 12mm (1.6)(1.5)(1.4)
Thikness of plaster for 2nd coat is fine 8mm (1.4)(1.3)
Area is 100sft/3.28^2=0.92
.92*.012=0.011
Sand 1cum required is 1.25cum
1.25/4=0.3125
0.01104*.3125*1440=50.19 Kgs Cement
(1.3)
Area = .92mtr sqr *.008(fine)=.0736*0.21=.0156*1440=22.48 Kgs Cement
| Is This Answer Correct ? | 11 Yes | 6 No |
Answer / prashanth kumar
MATERIAL REQUIRED FOR PLASTERING 100 SQUARE FEET OF CEILING WITH 12MM THICKNESS IN CM(1:3) IS 1.2 BAGS OF CEMENT AND IN CM(1:4) IS 1 BAG OF CEMENT
| Is This Answer Correct ? | 8 Yes | 3 No |
Answer / lawrence.m
We assume the thickness is approx. 0.5inch. So that the volume is 100sqftx0.5=50cft(1.416cum).
For 1 cum( CM1:4), 1/5x 1440= 288Kg cement required.
Therefore, 1.416cum = 407 Kg required(Approx 8 bags)
For CM 1:3, = 510 Kg (Approx. 10 bags)
| Is This Answer Correct ? | 10 Yes | 58 No |
residential projects,structural.
0 Answers Ambuja, KBR, Saudi Aramco Shell Refinery Company SASREF,
what is c4x light weight cement blocks
How do we say The LAP LENGHT is 50D to 60D ?????
What is proportion of PCC Grade G?
1. why steel used in concrete
how should we take soil sample for CBR test?
in one hour , one 200 excavator , how much quantity (mcube)can load ? soil is not hard not soft
0 Answers GKC Projects Limited GKCPL,
how many 10mm steel are needed in 99sqft room
what are the various types of pile foundation? explain with introduction
how to calulate coping material of boundry brick wall
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
What is the use of extend command?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)