9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement
Answers were Sorted based on User's Feedback
Answer / manikandan ramia sankaran
1. 9.00m x 9.00m x .15m
= 12.15 m3
12.15/(1+4+8)[x] 1.56 = 1.458m3 of cement
sand = 4 x 1.458 = 5.832 m3 of sand
4omm agg = 8 x 1.458 = 11.664 m3
| Is This Answer Correct ? | 7 Yes | 2 No |
Answer / bala
1. Consider 9.000m*9.000m*0.150m
Volume - 12.15Cu.m
* Cement - 41.31 Bags
* Sand - 6.075 Cu.m
* c.agg - 12.15 Cu.m
| Is This Answer Correct ? | 4 Yes | 5 No |
9*9*0.30m(assume your units) =24.3cum
cement=84.66 say-85 bags
sand=406.87 cft say-4.06 units
coarse aggregate=800.92 say-8 units
| Is This Answer Correct ? | 0 Yes | 2 No |
Answer / vikas
SUPPOSE - 9.00mtr.X 9.00mtr.X 0.20mtr. = 16.20 cum.
concrete.
Cement = 55.18 bags
fine aggregate (sand) = 7.72 cum.
coarse aggregate (metal) = 15.45 cum.
| Is This Answer Correct ? | 1 Yes | 4 No |
Answer / n.lakshmanan
9*9*.100=8.1m3
cement-26.244Bags
sand-67.29cft
40mm aggregate-134.58cft
| Is This Answer Correct ? | 0 Yes | 6 No |
Kindly tell me a book name to study for BIS exam
Define what is quality...
What is the factor of safety in civil engineering
kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com
230mm thick brick wall 10rmt length and 4.1 mtr high brick wall. tell quantity of cement,sand,brick required? Also tell me labour required to complete brickwall in 2days
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
how to calculate the strength of rebound hammer test reading in building construction ?
hi i am working in a civil Lab .....they asked me to find out the compressive strength of concrete cubes after 7 days of curing....the value of load on CCT machine is 205KN how to convert it to Kg/cm2 ....plzz help me...........
water leak detection system question & answer
How much quantity of rod binding work by a rod binder per day
why do we provide haunch for drains and culverts?
what is the percentage of Fly Ash content in cement and in concrete?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)