9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement
Answers were Sorted based on User's Feedback
Answer / manikandan ramia sankaran
1. 9.00m x 9.00m x .15m
= 12.15 m3
12.15/(1+4+8)[x] 1.56 = 1.458m3 of cement
sand = 4 x 1.458 = 5.832 m3 of sand
4omm agg = 8 x 1.458 = 11.664 m3
Is This Answer Correct ? | 7 Yes | 2 No |
Answer / bala
1. Consider 9.000m*9.000m*0.150m
Volume - 12.15Cu.m
* Cement - 41.31 Bags
* Sand - 6.075 Cu.m
* c.agg - 12.15 Cu.m
Is This Answer Correct ? | 4 Yes | 5 No |
9*9*0.30m(assume your units) =24.3cum
cement=84.66 say-85 bags
sand=406.87 cft say-4.06 units
coarse aggregate=800.92 say-8 units
Is This Answer Correct ? | 0 Yes | 2 No |
Answer / vikas
SUPPOSE - 9.00mtr.X 9.00mtr.X 0.20mtr. = 16.20 cum.
concrete.
Cement = 55.18 bags
fine aggregate (sand) = 7.72 cum.
coarse aggregate (metal) = 15.45 cum.
Is This Answer Correct ? | 1 Yes | 4 No |
Answer / n.lakshmanan
9*9*.100=8.1m3
cement-26.244Bags
sand-67.29cft
40mm aggregate-134.58cft
Is This Answer Correct ? | 0 Yes | 6 No |
what is the meaning of sleeves in reinforced concrete????. where its coming???.
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
what is the difference b/w GSB and WMM?
how to calculate the quantity of plaster.
how to convert cement, sand aggregate quantity from M3 to kg with full description?
How to calculate carrying capacity of the existing water supply trunkmain
what is the quantity of concrete required in 1 cubic meter volume without reinforcement
what is mean by bleeding of concrete
4 Answers Afcons, Habib Group,
How to calculate cement required for m20,m5 grade
Why we provide hair pin for shed
In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.
What is the difference between engineering stress and true stress?