Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


What should be the maximum allowable time for placing ready
mix concrete? The specification requires concrete placement
within 90 minutes of batching at the plant. What is the
significance of this 90 minutes & should this be used as a
rejection criterion? What effects does the concrete has
after that time period?


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Civil Engineering Interview Questions

What is passive earth pressure ?

0 Answers  


What material should be used for casting the beam-column junction if beams and columns are of different grades?? For example concrete in beams and Columns is M20 and M25 respectively.

1 Answers   DLF,


what is the name of software for designing of R.C.C.structures

10 Answers  


What is Definition Of Refuse Area In Building ? 

1 Answers   Arpee Group, Dudhwala Builders,


What is the curing period for Epoxy grouts

1 Answers  


What is the functional difference between DOME and R.C.C., where purpose of both covering roof?

2 Answers  


What do you meant by gui?

0 Answers  


What is allowable limit of silt in river sand for concrete

3 Answers   UIPL,


HOW MANY CEMENT BAGS ARE REQUIRED FOR 1m^2 PLASTERING AREA?

1 Answers  


What is the Oneday Productivity for 1 Skilled Carpenter and 1 Steel fixer?

2 Answers   GP Construction,


Types of column foundation and how to calculate its steel quantity.

0 Answers  


How much cement ,steel bar, concrete ,required for 416 cum rcc slab

1 Answers   ABC,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)