9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement
Answer Posted / bala
1. Consider 9.000m*9.000m*0.150m
Volume - 12.15Cu.m
* Cement - 41.31 Bags
* Sand - 6.075 Cu.m
* c.agg - 12.15 Cu.m
| Is This Answer Correct ? | 4 Yes | 5 No |
Post New Answer View All Answers
as per is code, what is the minimum content of opc and ppc cement for rcc structure
Prepare a Schedule for a Highrised building from starting stage to Handover?
What is the difference between pvc,cpvc and upvc and where it is used as per their properties?????
What do we mean by partial moment release ??
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
How do you determine specific gravity of cement?
For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
calculate the quantity of water for 1:6 cement mortar
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
What is thumb rule in quantity and cost estimation of a residential building?
Give me an example of a time when something you tried to accomplish and failed.
How to calculate chejja reinforcement