9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement
Answer Posted / manikandan ramia sankaran
1. 9.00m x 9.00m x .15m
= 12.15 m3
12.15/(1+4+8)[x] 1.56 = 1.458m3 of cement
sand = 4 x 1.458 = 5.832 m3 of sand
4omm agg = 8 x 1.458 = 11.664 m3
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
acceptance criteria for concrete works
LET ME KNOW HOW IS CALCULATE RUBBLE WALL .3'00" IN BOTTOM 1' 6" IN TOP HEIGHT 8' 0" AVERAGE. length 200'00". please give correct answer.
how to calculate the crushing strength of cement concrete paver blocks 100x100x60 mm thich.
What is the difference between engineering stress and true stress?
What is the likely strength of a 1:2:4 concrete mix?
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
Which brick is best for construction ,either fly ash or AAC BLOCKS
how many re use can use shutting material. timber ? ply? steel? plastic? fibre? aluminium? Doka?
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
How to calculate material and labor required for 100 m2 plaster?
16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.
Minimum concrete cover in slabs, columns, beams, foundation and other st?
How to calculate the quantity of ingredients of M20 grade concrete?