9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement

Answer Posted / manikandan ramia sankaran

1. 9.00m x 9.00m x .15m
= 12.15 m3

12.15/(1+4+8)[x] 1.56 = 1.458m3 of cement
sand = 4 x 1.458 = 5.832 m3 of sand
4omm agg = 8 x 1.458 = 11.664 m3

Is This Answer Correct ?    7 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.

1523


what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)

1617


why is the column design?

1913


HOw much % of premium on DSR-2013 currently

1618


what is escalation?how it is done?

2184






what is civil enginnering & what you need of this course?

1884


Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required

1642


what pressure the NP2 class RCC pipe can sustain?

2319


how to stop beam concrete between column

2013


04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1

1683


Please let me know what is the simplest way of Calculating Mix Designs

1640


what is your role of in previous company as a construction manager

1692


Why are steel plates inserted inside bearings in elastomeric bearing?

925


Define What does civil status mean?

879


I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?

1760