9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement
Answer Posted / manikandan ramia sankaran
1. 9.00m x 9.00m x .15m
= 12.15 m3
12.15/(1+4+8)[x] 1.56 = 1.458m3 of cement
sand = 4 x 1.458 = 5.832 m3 of sand
4omm agg = 8 x 1.458 = 11.664 m3
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
Why are steel plates inserted inside bearings in elastomeric bearing?
How to cal. The weight of hollow pipe?
What is passive earth pressure ?
what is column foundation
writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order
types of survey and levelling instrument ?
What is the use of array command?
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
I just got a first job in Maharashtra and m a fresher. My task is estimate the cost of excavation of earth with J.C.B. can anyone tell me how to do this??
1.Why we are preferring 43 grade cement than 53 grade cement. 2. Approximate cost difference between 43 and 53 grade cement. Thanks.
A sieve analysis results in 100% retained in no. 50 Sieve, the fm is?
Test procedure of fly ash bricks as per code ?
Formula for calculating the volume of bulb in underreamed pile
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
5. Do you feel that your present employer estimates your full work potential? Are they pleased with your work performance?