How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answer Posted / manoj kumar moharana
cement mortar ratio is (1:5)
assume the area that we are going to calculate the plaster qty is,
L = 3.048 m
B = 3.048 m
given H = 10 mm = 0.01 m
hence the qty is = 3.048 x 3.048 x 0.01 = 0.093 cum
add 30% of the above qty for joints = 0.093 x 0.3 = 0.028
total qty = 0.093+0.028
=0.121 cum
add more 25% for dry volume = 0.121 x 0.25 = 0.03
total qty =0.121+0.03= 0.151 cum
no. of cement bags = 0.151/(1+5) =0.025 cum / 0.0347= 0.720 bags
= 1 apprx.( where as 0.0347 is the volume of 1 bag cement)
qty of sand = 0.025 cum x 5 = 0.125 cum
therefore mortar reqd. for 1:5 cement plaster is
cement = 0.025 cum = 0.720 bag
& sand= 0.125 cum
| Is This Answer Correct ? | 28 Yes | 5 No |
Post New Answer View All Answers
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
where can i get the previous question papers for rrb section enginerr (civil)
How much is the cover for slab?
For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.
Scaffolding IS code NO.
qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
What Are The Different Type Of Slump Test Indications?
a concrete mix 1 2 4 by volume with water cement ratio as .6 by weight if moisture content in F.A is 6% with 20% BULKING AND IN C.A 1.5% by volume. find quantities of different materials required for one bag of cement
I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item
how much used soil in 1 brick of standard size?
How to calculate Cement in bags ,sand in sqft and aggregate in sqft for 1cum M25 grade concrete
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
What are the methods in tiles flooring ? What are the methods in brick work? What are the methods in plastering ? What are the methods in wall tiling?
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?