How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answer Posted / linu t mathew
Area to be plastered = 10'*10' = 100'
= 100/10.76 = 9.29sqm
(ie; 1 sqm = 10.76 sqft)
Thickness of mortar layer = 10mm = 0.010m
Volume of mortar required = 9.29*0.010 = 0.09cum
Add 15% for allallowance for calculation of surface and
wastages = (15/100)*.09 = 0.013 cum
Therefore, total volume of mortar required = .09+0.013 =
0.103 cum, say 0.10cum
Sand required for 0.10cum of CM 1:5 = 0.10 cum
Cement required for 0.10 cum of CM 1:5 = (1440/5)*0.10
= 288*0.10 = 28.8 kg
(ie; 1 cum of cement weighs 1440 kg)
| Is This Answer Correct ? | 42 Yes | 25 No |
Post New Answer View All Answers
difference between fc and fc'?
1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM
std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30
How should we design a brick column and footing?(note: no reiforcement to be provided) Can you tell me any reference book where i could possibly find this design? Plz help urgently
construction workers how much time take one work or qty
115mm thickness brick work how to required mortar
indian standard split spoon sampler
Which ratio use for cement selery???
Define block?
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
Can a wave happen in the middle of the ocean like in the movie poseidon 2006?
VAT and CST ? Which benefits for buyer ? Why benefits?