why we always consider Bulkage due to the voids only for
the Fine aggregates not for the Coarse aggregates

Answers were Sorted based on User's Feedback



why we always consider Bulkage due to the voids only for the Fine aggregates not for the Coarse ag..

Answer / suresh

free moisture forms a film around each particle. because of the surface tension of the water, the moisture film exerts a sort of pressure which keeps the fine aggregate particles away from each other.therefore it occupies more volume compared to dry condition.so, when we are adopting volumetric batching we actually use less volume of F.A, which makes the mix richer.
however this effect less pronounced(can take place) in case of
coarse aggregate. so we consider bulking is problem only for F.A.

Is This Answer Correct ?    11 Yes 2 No

why we always consider Bulkage due to the voids only for the Fine aggregates not for the Coarse ag..

Answer / d v n potharaju hyderabad

When moisture content is added,a seperating film is
formed with fine aggregate only .And the coarse aggregate
colld not form the film.
This seperating film is responsible for the bulking
of sand i.e fine aggregate.

Is This Answer Correct ?    9 Yes 4 No

why we always consider Bulkage due to the voids only for the Fine aggregates not for the Coarse ag..

Answer / bhushan narvekar

When moisture content is added,a seperating film is
formed with fine aggregate only .And the coarse aggregate
colld not form the film.
This seperating film is responsible for the bulking
of sand i.e fine aggregate.

Is This Answer Correct ?    2 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

Required concret Surface Temperature prior to coating of epoxy pain with references ASTM or ACI whatever

0 Answers  


how much quantity of binding wire required for tieing of 1mt of reinforcement bar?

5 Answers  


what are the types of trusses

1 Answers  


How many solid blocks can build one mason per 8 hours?

1 Answers  


Define aligned dimension?

0 Answers  






How much steel required for only ground floor of 1600 Sq foot.Having general structure ?

1 Answers   Alpine,


deshuttering time for RCC for DPC over the foundation.

4 Answers  


How many bricks are required for 100 sq ft 5" & 3" wall, Brick size= 230x115x75

3 Answers  


Kindly post me previous year interview questions with answer for post of Manager (civil engg.) for NTPC, IOC , GAIL etc. I have interview on july 2013.I will be very grateful to you. Please guide me.

0 Answers   NTPC,


how much cement and sand is used for plastering 1646 sq feet,for 12mm thickness and ratio 1:4

3 Answers   L&T,


what is the minimum and maximum water cement ratio

6 Answers  


sir, how to calculate steel per 1 m2

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)