why we always consider Bulkage due to the voids only for
the Fine aggregates not for the Coarse aggregates
Answers were Sorted based on User's Feedback
Answer / suresh
free moisture forms a film around each particle. because of the surface tension of the water, the moisture film exerts a sort of pressure which keeps the fine aggregate particles away from each other.therefore it occupies more volume compared to dry condition.so, when we are adopting volumetric batching we actually use less volume of F.A, which makes the mix richer.
however this effect less pronounced(can take place) in case of
coarse aggregate. so we consider bulking is problem only for F.A.
| Is This Answer Correct ? | 11 Yes | 2 No |
Answer / d v n potharaju hyderabad
When moisture content is added,a seperating film is
formed with fine aggregate only .And the coarse aggregate
colld not form the film.
This seperating film is responsible for the bulking
of sand i.e fine aggregate.
| Is This Answer Correct ? | 9 Yes | 4 No |
Answer / bhushan narvekar
When moisture content is added,a seperating film is
formed with fine aggregate only .And the coarse aggregate
colld not form the film.
This seperating film is responsible for the bulking
of sand i.e fine aggregate.
| Is This Answer Correct ? | 2 Yes | 1 No |
How to calculate the design of column by simple method?
If the design CBR of subgrade is 10% but the material available on site is 30%.will you compact less(like 90%) where you get desirable CBR(10%).
how the centre of gravity is used in construction?
why seismic analysis not done during design of slabs
what is the difference between gypsum and pop?
WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?
how to take concrete quantity for precast segment for viaduct project?
material calculations for I st coatplastering 16mm CM (1:5),second coat CM(1;3)4mm thick,pcc(1:4:8),RCC M20,lime stone masonry CM(1:6)
For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?
what"s the formula to find the cement,sand,aggreegate(45mm) requirement for PCC?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
What is the thickness of slab for 600 sq each) 2 slab construction. What should be the size of steel rod?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)