Please tell me the difference between nominal and clear
cover. Thanks.
Answers were Sorted based on User's Feedback
Answer / pvsnrao
Let us take, b = bredth of the beam
D = Overall depth of the beam.
Effective depth = overall depth-effective cover
effective cover = the distance from botttom of fibre of the
beam to the centre of reinforcement.
Clear cover = the distance from the bottom of fibre to
bottom level of the reinforcement
| Is This Answer Correct ? | 209 Yes | 23 No |
Answer / h. pradeep nair
nominal cover and clear cover are the same. both are the cover from the outer concrete to the outer face of the stirrups. latest revision of IS 456 says that NC is same as clear cover
| Is This Answer Correct ? | 89 Yes | 19 No |
Answer / mustafa mohd layeak
In beam of b*D dimension. considering bottom section of beam
effective cover is the distance between centre of main
bottom longitudinal rebar to the concrete extreme fibre
(bottom edge of beam).
clear cover is distance between concrete extreme fibre and
bottom edge of a stirrup
Similarly at the top section of beam
| Is This Answer Correct ? | 45 Yes | 8 No |
Answer / suchith kumar
effective cover=the distance from centre of iron rod to the bottom of fibre.
clear cover=the distance from bottom of fibre to bottom of iron rod.
| Is This Answer Correct ? | 20 Yes | 6 No |
Answer / joydeep dhar
Nominal cover means clear distance between face of concrete and face of main outer rebar, whereas effective cover means center of rebar to outside of concrete face, so Nominal cover < effective cover. viz. if 20 dia steel is used and nominal cover is 40mm then, effective cover will be (40+(20/2))= 50mm
| Is This Answer Correct ? | 12 Yes | 8 No |
Answer / ashis pal
please tell me cover use beam & column- main bar / stirrups .
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / binubal123
In nominal cover half diameter of the beam is added along with cover depth whereas in clear cover only depth of cover is included.
| Is This Answer Correct ? | 15 Yes | 59 No |
Answer / suraj verma
Clear cover is the distance between C.G of reinforcement bars and bottom most point of concrete.
Whereas ominal cover is the end to end distance of r/f bars and botom most point of concrete.
| Is This Answer Correct ? | 1 Yes | 45 No |
On concrete surface 1sq.ft area hacking no's of hack?
Can anyone tell me the thumb rule for calculating structural steel quantity?
If we know the N - Value of soil and required bearing capacity how do we know what diameter and length of pile to be casted? How can we check whether the dia. and lenght of pile we have selected are most economical onse?
why demand factor less then 1 ?
How can we compact the soil on slope portion? What is the Grade II of Stone Metal?What type tests carried out on BBM road?
How to calculate density(dry & bulk) of sand from Sp. ravity value of sand. eg. G=2.5
If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)
what is the ratio of M10,M20,M30,M40,M50,M60 grade concrete
28 Answers NCC, PWD, SPML, Student,
What is the difference between routing maintenance and major maintenance in school facilities?
Mix proportion of M30 grade?????????
Moisture content calculation for diff mix ratio's ??
Direct chairs over shutter / beside earth is prohibited because of ––
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)