Answer Posted / priya
In the construction of RC buildings, due to the
limitations in available length of bars and due to
constraints in construction, there are numerous
occasions when column bars have to be joined. A
simple way of achieving this is by overlapping the two
bars over at least a minimum specified length, called
lap length. The lap length depends on types of
reinforcement and concrete. For ordinary situations, it
is about 50 times bar diameter. Further, IS:13920-1993
prescribes that the lap length be provided ONLY in the
middle half of column and not near its top or bottom
| Is This Answer Correct ? | 28 Yes | 2 No |
Post New Answer View All Answers
What goals do you have in your career?
What is standard Sand? What is Regime condition? What do you mean by the core trench in Earthen Dasm? What is soundness test for cement? When negetive shear force takes place in a R.C.C member?
types of laps in column
What is the different type of slump test indications?
How do you calculate the unit weight of concrete?
How do we calculate absolute pressure?
What are the responsibilities of a construction manager?
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3
what else we can add rather than admixture in concrete to reduce the cement quantity?
what is tension footing?
115mm thickness brick work how to required mortar
What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?
I have to design brick column and footing (note: without any reinforcement). Can somebody post me the design or suggest a book where i could possibly find the design? Plz help very urgent
1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...