Answer / maheswaran
Calculation of Materials:-
For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
Wall plastering in CM 1:4 of 12 mm thick for 100 m2:-
Volume = 100 x (12/1000) = 1.20 m3
Add 30 to 35% as bulking of sand = 0.36 m3
Add 20 as wastage of sand = 0.312 m3
Total = 1.872 m3
= (1.872/1+4) = 0.374 m3
Cement = 0.374 x 30 = 10.77 bags
Sand = 0.374 x 4 =
1.496 m3
Is This Answer Correct ? | 71 Yes | 11 No |
Answer / karthi
For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
Volume = 100 x (12/1000) = 1.20 m3
Add 30 to 35% as bulking of sand = 0.36 m3
Add 20 as wastage of sand = 0.312 m3
Total = 1.872 m3
= (1.872/1+4) = 0.374 m3
Cement = 0.374 x 30 = 10.77 bags
Sand = 0.374 x 4 =
1.496 m3
Is This Answer Correct ? | 22 Yes | 4 No |
Answer / sunee.p
Calculation of Materials:-
For 1 cum of concrete Mix 1:2:4 (M15)
1 cum concrete volume = 1.57 cum
= (1/7)*1.57 = 0.224 cum
For 1 cum = 30 bags of cement required (1440/50) say 29 bags
Cement = 0.224 x 29 = 6.496 bags
Sand = 0.224 x 2 = 0.448 cum
Aggregate = 0.224 x 4 = 0.896 cum
Wall plastering in CM 1:4 of 12 mm thick for 100 m2:-
Volume = 100 x (12/1000) = 1.20 cum
Add 30 as bulking of sand = 0.36 cum
Add 20 as wastage of sand = 0.312 cum
Total = 1.872 cum
= (1.872/1+4) = 0.374 cum
Cement = 0.374 x 3 = 10.77 bags
Sand = 0.374 x 4 = 1.496 cum
Is This Answer Correct ? | 9 Yes | 3 No |
what is water cement ratio in design mix and its percentage in concrete and mortar?
1 Answers Jain Housing, Shivshakti Sugars, Tulip,
which is the period is known as golden period in ancient india?
how many shuttering material required for 1000 sq.m built up area.
give me the mix proportion for design mix concrete M10 grade 1:4:8
13 Answers Gammon, IOCL, PSL, SDG, Simplee, STUP Consultants Pvt Ltd,
Are you interested in starting a fly ash brick making unit?
Deshuttering time for slab 6.15 meter
how to calculate the weight of concrete
Key is put at the time of casting 1st lift of column to get– –
Can we provide lapping of R/f steel for plinth beam in support portion(At column)?
7. Do you apply the skills and knowledge learnt at school in your work?
How foundation is designed, Column design and beam design
How to deduct block quantity from the slab quantity for concreting for slab.????