how to calculate amount of materials for concreting and
plastering?
Answers were Sorted based on User's Feedback
Answer / maheswaran
Calculation of Materials:-
For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
Wall plastering in CM 1:4 of 12 mm thick for 100 m2:-
Volume = 100 x (12/1000) = 1.20 m3
Add 30 to 35% as bulking of sand = 0.36 m3
Add 20 as wastage of sand = 0.312 m3
Total = 1.872 m3
= (1.872/1+4) = 0.374 m3
Cement = 0.374 x 30 = 10.77 bags
Sand = 0.374 x 4 =
1.496 m3
| Is This Answer Correct ? | 71 Yes | 11 No |
Answer / karthi
For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
Volume = 100 x (12/1000) = 1.20 m3
Add 30 to 35% as bulking of sand = 0.36 m3
Add 20 as wastage of sand = 0.312 m3
Total = 1.872 m3
= (1.872/1+4) = 0.374 m3
Cement = 0.374 x 30 = 10.77 bags
Sand = 0.374 x 4 =
1.496 m3
| Is This Answer Correct ? | 22 Yes | 4 No |
Answer / sunee.p
Calculation of Materials:-
For 1 cum of concrete Mix 1:2:4 (M15)
1 cum concrete volume = 1.57 cum
= (1/7)*1.57 = 0.224 cum
For 1 cum = 30 bags of cement required (1440/50) say 29 bags
Cement = 0.224 x 29 = 6.496 bags
Sand = 0.224 x 2 = 0.448 cum
Aggregate = 0.224 x 4 = 0.896 cum
Wall plastering in CM 1:4 of 12 mm thick for 100 m2:-
Volume = 100 x (12/1000) = 1.20 cum
Add 30 as bulking of sand = 0.36 cum
Add 20 as wastage of sand = 0.312 cum
Total = 1.872 cum
= (1.872/1+4) = 0.374 cum
Cement = 0.374 x 3 = 10.77 bags
Sand = 0.374 x 4 = 1.496 cum
| Is This Answer Correct ? | 9 Yes | 3 No |
Bernaullis theorem deals with the law of conservation of mass momentum energy none
What is the density of 1:1.5 (Cement:sand) ratio in plaster? And Conversion in 12.5 mm thickness per square meter? Howmany Kg of Cement square meter in ratio of 1:1.5?
can we go for short rcc column without any steel rienfocement carrying truely axial load only???(No other load acting on it such as wind load,earthquake & lateral earth pressure)
WHAT HAPPEN WHEN USING OF LARGEST POSSIBLE MAXIMUM SIZE AGGREGATE RATHER THAN SMALLER AGGREGATE IN RCC ?
how many BSCs can i connect to the HUAWEI MSC
12mm diameter iron bar having 1m length how much kg weighted ?
How Can You Design Aisolated Footing Subjected To Tenstion Force?
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
How to Concrete cube test method and required result in 3days & 7days & 28 days, for all grade of concrete which refer the is code no.
If the proportions of concrete is a:b:c i.e if "a" parts of cement,"b" parts of fine aggregate & "c" parts of coarse aggregate are mixed by volume. Then the resulting volume will have a volume of ------? How?
How to take steel quantity for beams ?how to calculate stirrups
.5Ast
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)