Project at andheri west mumbai total area of 116000 sq ft near by..Please help me out for quotation plan is ready basic details are with me , please help me out .I will mail u in autocad also.



Project at andheri west mumbai total area of 116000 sq ft near by..Please help me out for quotation ..

Answer / arbaz shaikh

16922sq ft=basement,
32022sq ft=super structure rehab
69087sq ft= for sale structure
Scope of work-rcc work,brick(siporex)block work,plaster.
Concrete(m-25 to m-50) -1.25cft.Sqft of bua,(for super structure.
4cft sqft of bua (for basement)
Consumption of steel(fe 550d) -5.5 kg sqft of bua for super structure.
12 kg sqft of bua for basement
What should quotation for this please guyz help me out .?

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what is the difference between weir and a barrage

12 Answers   AAI Airports Authority Of India, CIT, TCI Constructions,


can we go for short rcc column without any steel rienfocement carrying truely axial load only???(No other load acting on it such as wind load,earthquake & lateral earth pressure)

2 Answers   Lodha,


How much percentage of overlap allowed in distribution steel as per IS Code.

2 Answers   Don Consult, India Cements,


how much need cement bags for block work of wall approx 1000 hollow blocks 20x20x40cm

0 Answers   MFAR,


i have a bar of 20 and 16, lap length is 48*dia of bar, what is the lap length here

8 Answers  






what is mean by bPo in construction? pls tell me

1 Answers   Sangini, SRM, SV,


How Calculate Lap Length

10 Answers   L&T,


Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.

0 Answers   GAIL, KOC, Megha Constructions,


how the find the quantity of water used to make 1 cubic meter concrete mortor

1 Answers   Appco,


Laboratory experiments conducted in Mumbai on a particular mix showed a strength of 33 MP a for a fully matured concrete. Find whether formworm can be removed for an identical concrete placed at Jammu at the age of 15 days when the average temperature is 60C. The stripping stress in concrete

2 Answers   CCIL,


What are the ingredients of pre-stressed concrete?

0 Answers  


how much kg of binding wire is used in slab ?

4 Answers   L&T, Standard,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)