Number of cement bags required for concreting 1000 square
Feet slab of 4 inch thickness.
Answers were Sorted based on User's Feedback
Answer / mohammedazhar uddin
for the grade m20 the cement per 1cum is 320kg
so the quantity is calculate in this manner
1000*4"=9.42 cum
then 9.42*320=3014kg 1bag= 50kg than
3014/50=60.2bags
| Is This Answer Correct ? | 88 Yes | 35 No |
Answer / raghav gowda
for 1000sqft slab of 4" thk.
assume for M20 grade of 350kg cement for 1cum of concrete is
first convert the 4" thk to feet i,e 4/12= 0.333'
then, 1000x0.333= 333cft
convert 333cft to cmt i e, 333/35.28=9.438
for 9.438cmt of concrete cement required is 9.438x350=3303.3kg
then convert it in to bags
3303.3/50=66.066bags
so the cement reqired is 66.066bags.
| Is This Answer Correct ? | 67 Yes | 27 No |
Answer / ashwini
If the grade of concrete is M25 and 330 KG cement per cubic
meter of concrete. Then the answer is 61.31 bags of cement
is required.
| Is This Answer Correct ? | 39 Yes | 26 No |
Answer / dharmendra barot
For 1000 sq ft 4"thick use M20 (1:1.5:3) for cement required 71 bags
| Is This Answer Correct ? | 26 Yes | 14 No |
Answer / somu
1000 Sq.ft= 92.9 Sqm
4 inches= 0.1 m
volume= 92.9*0.1= 9.29 Cum
M20 Grade
Cements bags= 0.29*(0.46/1.5)*1440=4102.464kgs/50 kgs= 82 Bags
| Is This Answer Correct ? | 13 Yes | 6 No |
Answer / sindhu
If grade is M10 (1:3:6), cement in kgs per cum is 266kgs
1000 sq ft
4 inches=4/12=0.33ft
1000*0.33=330 cft
330/35.315(1 cum= 35.315 cft) = 9.344cum
9.344*226(cement in kgs per cum) =2111.85 kgs
2111.85/50(per bag) = 42.23 bags
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / remesh babu pillai .k .p
Theoretically -61.3 bags .practically it comes 55.8 Bags
| Is This Answer Correct ? | 0 Yes | 2 No |
explain about earth quake zones? Chennai falls under which zone
what is the significance of bending moment in a structure?
how to calculate the lap bar for bor culvert ?
what is penetration test?why it is done?
what motivates you to do a good job
1 Answers Flextronics, HPCL, ISRO,
what is the types of surveying?which type of survey carrying for type of work?
i have boiler of 35 tone and wanted dig out foundation is there any body to help me to carry out calculation for the foundation like
waht is the angle of reposae
how to absorb to site basic corrections? which are the important correction?
Which types of Water Proofing to Be used in Swimming Pool.
2 Answers CCEL, Ideal Construction,
how to calculate quantity of steel in a slab , coloumn and beam
1 Answers JSW, Om Sai Builders,
What is the ratio of materials used for M10, M15, M20 & M25 grades of concrete? Also specify the quantity of water used in each grade & how to calculate it?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)