Calculation of Materials:-
For 1 cum of concrete Mix 1:2:4 (M15)
1 cum concrete volume = 1.57 cum
= (1/7)*1.57 = 0.224 cum
For 1 cum = 30 bags of cement required (1440/50) say 29 bags
Cement = 0.224 x 29 = 6.496 bags
Sand = 0.224 x 2 = 0.448 cum
Aggregate = 0.224 x 4 = 0.896 cum
Wall plastering in CM 1:4 of 12 mm thick for 100 m2:-
Volume = 100 x (12/1000) = 1.20 cum
Add 30 as bulking of sand = 0.36 cum
Add 20 as wastage of sand = 0.312 cum
Total = 1.872 cum
= (1.872/1+4) = 0.374 cum
Cement = 0.374 x 3 = 10.77 bags
Sand = 0.374 x 4 = 1.496 cum
Is This Answer Correct ? | 9 Yes | 3 No |
Post New Answer View All Answers
Define What glue is least sticky?
What is capicity of cap lock scffolding stander(vertical member) and ledger of different size?
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
Trapezoidal section footing calculation of Volume & its Area
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
How to calculate carrying capacity of the existing water supply trunkmain
Power grids in two adjacent states(A&B) are interconnected. Can power grid in state A can be represented by Thevenin Equivalent Circuit. If not explain Why?
Explain the difference between shear and tensile strength.
I HAVE APPLIED FOR 20TH UES ARMY. I WANTED TO KNOW WHEN WILL I RECEIVE CALL LETTER FOR THE SAME.
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
Differentiate orthographic and isometric projections?
what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
How many axes do cartesian coordinate system has?