Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to calculate amount of materials for concreting and
plastering?

Answer Posted / sunee.p

Calculation of Materials:-

For 1 cum of concrete Mix 1:2:4 (M15)
1 cum concrete volume = 1.57 cum
= (1/7)*1.57 = 0.224 cum
For 1 cum = 30 bags of cement required (1440/50) say 29 bags
Cement = 0.224 x 29 = 6.496 bags
Sand = 0.224 x 2 = 0.448 cum
Aggregate = 0.224 x 4 = 0.896 cum

Wall plastering in CM 1:4 of 12 mm thick for 100 m2:-

Volume = 100 x (12/1000) = 1.20 cum
Add 30 as bulking of sand = 0.36 cum
Add 20 as wastage of sand = 0.312 cum
Total = 1.872 cum
= (1.872/1+4) = 0.374 cum
Cement = 0.374 x 3 = 10.77 bags
Sand = 0.374 x 4 = 1.496 cum

Is This Answer Correct ?    9 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you

2552


5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)

2086


calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick

1749


Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem

2701


What is Rankine Cycle?

1035


if the nitrates more than 45mg/l in water lead to disease then what is it called

2868


In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.

3264


What are some structures that may be subjected to fatigue?

1075


how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend

1984


Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day

1995


Explain the latest method to detect a crack in a building?

1120


What the advantages and disadvantage of using 90mm and 100mm bricks for a wall of a house? Thanks for any input.

1928


pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer

3037


What are the uses of groynes?

1070


why do we not deduct volume of steel to find actual volume of concrete in practical???

1741