Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


A genarator is connected through a 20MVA ,13.8/138 KV
stepdown transformer to a transmission line. at the
reciving end of the line a load is supplied through a step
down transformer of 10MVA,138/69 KV rating .A 0.72 PU load
evaluated on load side transformer ratings as base
values ,is supplied from the above system for system base
values of 10 MVA and 69 KV in load circuit the value of the
load in generator circuit will be ...........



A genarator is connected through a 20MVA ,13.8/138 KV stepdown transformer to a transmission line...

Answer / ram

load in the generator circuit will be is 36

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

why dc supply is given for excitation of ac alternator?how dc can produce flux?

5 Answers  


what is soft starter? what is the difference between soft starter and star delta starter?

1 Answers  


are you hear the meaning of burden , excat meaning of burden in only one word

4 Answers  


Whis machine is having higher efficiency Transformer or Generator

2 Answers  


Why diesel tank kept in 990 ltrs

1 Answers   Reliance,


What are the main advantages of generalized error co-efficients?

0 Answers  


what is daiod

4 Answers  


If auto trip is operated, can you close the breaker.

2 Answers   KSEB, L&T, Siemens,


can we ran equipment up to 10kw between phase to grounding/ earthing. beside above can we use grounding instead of neutral. .

1 Answers   TNEB Tamil Nadu Electricity Board,


how much speed will trawiling current

3 Answers   TCS,


WHY IS THE EARTH FAULT CURRENT ALWAYS LESS THAN THE NORMAL CURRENT??

7 Answers   Reliance,


Describe the test procedure to determine the vector group

0 Answers   MPSEB,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)