What are the testing to be done before the installation of
1000 KVA Transformer?
Answers were Sorted based on User's Feedback
Answer / jyotirmaya
Normally test are done before installation and commissioning
of the transformer. The following test are done;
1. Visual Inspection
2. Insulation Resistance Test
3. Ratio Test
4. Vector Group Test
5. Magnetizing Current Test
6. Core Balance Test
7. Winding Resistance Test
Is This Answer Correct ? | 38 Yes | 3 No |
Polarity Test also an important before loading
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / rajan singh tanwar(j.k. cement
For Power
Transformers the
following Pre
Commisioning tests
are done:-
1.Visual Inspection
2.Measurement of IR
Value
3.Measurement of P
I Value
4.Measurement of
Winding
Resistance
5.Short Circuit Test
6.Oprn Circuit Test
7.Magnetic Core
balance Test
8.Voltage Radio Test
9.Oil BDV & Acidity
Test
10.Checking the
function of
OTI, WTI, OSR, MOG,
PRV
Relays
Last one for the
relay's testing but
it also comes under
transformer testing.
Thanks
Is This Answer Correct ? | 3 Yes | 0 No |
Why are calling lagging power factor is a inductive load?
how can we calculate air compressure capacity
NGR? What is NGR?
Do u know any one? how to find out in motor rated amps? formula?
What is fault level? How can be calculate the fault level?
What is the following which is printed on electrical appratuses like AC21 ,AC 23 , etc ?
what is mean by NTPC?,why didn't electric shock in train?
I am abt to give IOCL intrv.Plz sir guide me for IOCL intrvw (Electrical).Which subject to be consider. questions are generally asked from which subject.Plz help me out.
how to estimate the breaker capacity of breaker,please give the one example( 6.6 kv breaker,800a)?????
How does the sensitive earth fault protection provided by cbct for motor can help in reducing the size of cable used to supply the motor?
how to calculate micom relay earth falt time and current sertting
While testing LA mast,What are the parameter limits ?