If at site iam supposed to get M30.But by mistake i got M20
mix. How could I differentiate the mix before placing?
Answers were Sorted based on User's Feedback
Answer / nagori salim
R.M.C. supplier always provide Challan with each transit.
The Challan clearly shows the grade of concrete & the
quntity of ingredients in it, which differentiates the mix.
| Is This Answer Correct ? | 17 Yes | 1 No |
Answer / girish rawat
Always insist on Computer Batch reports from RMC suppliers.
It is always recommended to use Highlighter on Grade of
Concrete and Time of Batching for Quality Check
| Is This Answer Correct ? | 6 Yes | 1 No |
Answer / pramod
In case of this thing u cannot differentiate the mix before
placing. If this is possible then client also check it out
before placing.
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / alibaba
hi friends
cast the cubes 150*150*150mm and see the compressive strength of cube after 3 7 14 and 28days
| Is This Answer Correct ? | 3 Yes | 7 No |
Answer / chouhan
Dear
I dont think its useful instead of M30 to put M20 becose u have difrent like M20 is 20N/mm2 and M30 is 300n/mm2.
If you have any other solution pls share with so we can also use it on site.......... off course should get approval before apply.
| Is This Answer Correct ? | 0 Yes | 6 No |
fiends iam trying to solve if it correct reply me
take a container put 0.1 cu.m of concrete add some water in
it slowly try to drain out water separate sand and aggregate
weight it covert the obtained weight to 1 cu.m you come to
know the mix is m30 or m20
| Is This Answer Correct ? | 8 Yes | 23 No |
what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?
What is cold joint, what will happen due to cold joint?
differance bet QA & Qc
what is the ratio of cement water and sand in RCC?
1) what do you mean by rolling margin of steel ? 2)pls. tell the cut length formula of stirrups as per IS codes(take out cut length for a beam of 600*300mm with 40mm cover all sides)? 3)what is the multiplying factor of painting for sand faced plaster? 4)if your footing is of size1.9*1.6m . what quantity of length and width you will excavate means what extra margins you will allow as per IS codes in billing?
Time required for curing of wall tiles before fixing
How Mney Layers in 8mm plywood
what is the diffrence between Specific gravity & Density??
How to do base isolation using ETABS software?
why cylinder for split tensile strength test ?
RCC MEANS
what is procedure to find the volume of material in M20 concrete?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)