WHAT ARE THE DATAS REQUIRED FOR SCS SIGNAL LIST PREPARATION?



WHAT ARE THE DATAS REQUIRED FOR SCS SIGNAL LIST PREPARATION?..

Answer / a.p.nanjappa

It depends on your SUB STATION CONTROL SYSTEM (SCS)
supplier and client, and load despatching authority SCADA
system.
Generally Load despatching authority demand:
I) Remote control -on-off control oF CB,STATUS OF
INDICATION,PROTECTION AL+TRIP SIGNALS ,FEED BACK SIGNAL.
OLTC COUNTER,
2) INDICATION - A,V,F,PF, MW,MVAR,

3) METERING IN -OUT MWH,MVARH,

4) sTATUS OF ALL CB,DS,ES, PLC,

5) MAIN BUS ,INCOMMING,OUT GOING.

6)SUB STATION dc VOLTAGE, UPS ALARM

7)FAULT LOGGER REPEATITION SIGNAL.

THIS IS A VERY EXPENSIVE TASK. SCS SUPPLIER MUST FINALIZE
CLEARLY,AFTER FINALIZING SIGNAL SUCH ,AS DI,DO,AI,AO ,LOGIC
SEQUENCES, SHALL PROCEED HIS WORK.
tARIFF METERS ARE VERY EXPENSIVE. SCS MUST FOLLOW LOAD
DESPATCHING REGULATION AND ITS SPECIFICATION.

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

being an electrical engineer why you wanna come into software i have an very good academics what answer i have to give

0 Answers  


hello friends..... any one have papers or any study materials?sail ,hpcl...?

0 Answers  


In radial network the source is fed from 1 end both ends at central

0 Answers  


a 3 phase slip ring induction motor is wound for 4 poles on stator and 6 poles on rotor; when 3 phase balanced voltage source at 50 hz is applied to motor it will run at a)1500rpm b)1000rpm c)750 rpm d)zero rpm

13 Answers   Essar, PSPCL, PSTCL,


Define active and passive network?

0 Answers  






why is the transmission voltage is multiple of 11?

1 Answers   HAL,


For my plant the electricity department charging some amount for t/f losses. May i know what are transformer losses

1 Answers   L&T,


What should be ideal IR value for 11kV, un earthed, 1 MW motor?

3 Answers   Sail,


what is servo motor and how it works?

0 Answers   Godrej,


How to define Kirchhoff current law and voltage law along with simply examples.

0 Answers  


how convert kvar to microfarade? circuit diagram of infrared transmiter and receiver? circuit diagram of Fm transmiter and receiver?

2 Answers  


How much current will a 5 HP delta connected motor at no load will take?Is tat need a starter

2 Answers   GRB,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)