WHAT ARE THE DATAS REQUIRED FOR SCS SIGNAL LIST PREPARATION?

Answer Posted / a.p.nanjappa

It depends on your SUB STATION CONTROL SYSTEM (SCS)
supplier and client, and load despatching authority SCADA
system.
Generally Load despatching authority demand:
I) Remote control -on-off control oF CB,STATUS OF
INDICATION,PROTECTION AL+TRIP SIGNALS ,FEED BACK SIGNAL.
OLTC COUNTER,
2) INDICATION - A,V,F,PF, MW,MVAR,

3) METERING IN -OUT MWH,MVARH,

4) sTATUS OF ALL CB,DS,ES, PLC,

5) MAIN BUS ,INCOMMING,OUT GOING.

6)SUB STATION dc VOLTAGE, UPS ALARM

7)FAULT LOGGER REPEATITION SIGNAL.

THIS IS A VERY EXPENSIVE TASK. SCS SUPPLIER MUST FINALIZE
CLEARLY,AFTER FINALIZING SIGNAL SUCH ,AS DI,DO,AI,AO ,LOGIC
SEQUENCES, SHALL PROCEED HIS WORK.
tARIFF METERS ARE VERY EXPENSIVE. SCS MUST FOLLOW LOAD
DESPATCHING REGULATION AND ITS SPECIFICATION.

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

From past few months I am getting lagging pf even though sufficient capacitors used in circuit. Where is the problem pls answer

943


transformer phasor diagram under load explain it?

1675


hi all i like to know vat is power plot in control systems also i want to know abt latest trends in electrical & electronics

1468


Why squirrel cage motor can only use with low starting loads ?

1560


how hydrogen cooled alternator undergo maintanence ? that is hydrogen when come in contact with air can result into explosions .

1520






Describe the test procedure to determine the vector group

1603


1) Explain why we don't link the two earthing system ht and mv on a pole mounted transformer sub-station.

1290


Give details on how you intend to handle a challenging position you are posted to manage unexpectedly as a company staff?

2892


State Maximum Power Transfer theorem.

735


Why neutral cable carry current.

1524


If I have 3 essential main switch board and 3 incoming electricity ,but only 1 genset running is that possible.

1146


In the formula : Knee point voltage = Burden X alf / class, Please inform what is alf? regards Shashidhar M.R.

3402


what is the reason the main breaker is trip during the motor is running? (some time the breaker is not trip)

1309


what is circuit breaker in transfomer and where it used

737


how line turns ratio changes in 3 phase with change in connection

1424