Answer / sandy2004
CO06 is used for backorder processing.
Procedure
Access Backorder Processing
1. Call up the backorder processing.
You can call up the backorder processing using the
transaction CO06 The system calls up the initial screen
for processing backorders.
2. Enter the material number of the material to be
processed as well as the plant.
The system checks availability according to ATP logic.
The system calls the overview of backorder processing. In
this screen, the system displays the plant stock or the
storage location stock, the open sales orders or the
dependent reservations and the scheduled receipt elements.
The texts for the receipt and issue elements correspond to
the texts that appear in the MRP list. The various stocks
(individual customer stock, and so on) and the storage
locations are displayed and managed in separate segments.
Processing Sales Orders
The system highlights sales orders or customer requirements
that have not yet been completely confirmed or for which no
receipt has yet been scheduled. The missing parts are
displayed in the column Requirement/receipt.
1. Double-click the sales order or customer requirement,
which is to be confirmed.
In the lower part of the screen, the system displays the
detailed data of the selected sales order for the selected date.
The following data is displayed in detail:
o Open quantity
Total requirement quantity of the sales order or the
customer requirement.
o Material availability date
Date by which sufficient quantities of the item must be
available.
o Total confirmed quantity
Quantity that has been confirmed (in sales order management
when creating the sales order or in backorder processing).
o Confirmed quantity
In this field you can enter the quantity that is to be
allocated (that is, confirmed) in backorder processing.
o ATP quantity
Quantity which can be used when planning open requirement
quantities.
2. Enter the quantity which, according to the ATP
quantity, you can allocate to the requirements in the
Confirmed quantity field.
4. Save your entries.
Note
You can process backorders for sales orders only for
materials for which you have set the indicator Individual
requirements in the material master record (MRP 3 view,
Availability check field).
Dependent reservations, stock transfer requisitions and
stock transfer orders are processed at the same time.
Note
To do this, choose Settings ® Only SD requirements. From the
sales and distribution point of view, backorder processing
can also be set in such a way that only the requirements
necessary for SD are displayed as missing parts. From the
sales and distribution point of view, backorder processing
can also be set in such a way that only the requirements
necessary for SD are displayed as missing parts. To do this,
choose Settings ® Only order reservations.
Is This Answer Correct ? | 10 Yes | 0 No |
Answer / sham
Thanks Sandy for Nice Explination.
Can u send me ur mail ID.on my mailID
sham_sap@rediffmail.com
Is This Answer Correct ? | 0 Yes | 6 No |
Does delivery documents have any pricing procedure or condition types attached to it?
How many pricing procedures you have configured in the system and what are their purposes?
Third party sale?
How request transport fron one server to another and what is the role of functional and Basis consultant.
In which scenario we use F5 ,F1 ,F8 billing type ?
What is plant in sap?
what are the stages involved in VALUE SAP. please brief it
83. You can use customizing to control which business transactions should be blocked if the credit limit is exceeded? Which are they?
There is one legal entity IN10 under which there are 4 different plants 1, 2, 3 and 4. I have maintained plant number 1 in MMR and extended to plant 2, 3 and 4. Now I am creating one contract with plant number 2 however in material master data there is plant 1. with respect to Contract I am creating Debit Memo Request in DMR. However in DMR document i am getting plant 1 which I have maintained in MMR, However I have to get plant 2 which I have maintained in contract. Please tell me how to carry that plant 2 from contract to DMR ( RRB). Is it possible through standard SAP or Should I go to enhancement.
What is an outline agreement?
what is settlement profile...when i m doing varient configuration i am facing this problem while creating sales order plz explain me......
text determination in sales what is the header and item text?