What is relationship?
Answers were Sorted based on User's Feedback
Answer / subhrajyoti bhattacharjee
Relationship basically denotes how activities in a
networkorder are related to each other.They can be
classified into 4 categories - SS (Start-Start), SF(Start-
Finish), FF (Finish-Finish), FS (Finish - Start).
For 2 activities say A and B
SS -->> Both A and B start together
SF -->> Start of A coincides with finish of B and so on.
We can also specify the time gap between which these
relationships work. Say in an SS relationship, there can be
a 10 minutes gap between start of A and B and so on.
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / raja sekhar
relationship is nothing but reliation between the
activities. for ex: in any concern so many activities is
there, how to performe the activities is the, question here.
for ex:
let us see: if u want to built a building, then first u got
a approval from the govet., here 2 activities involved 1)u
built a house 2) u got a government approval, see here the
logic of relation ship is first u finish ur approval then
only u start a bulding, means here first activite closed and
2nd activity is start, this is called relationship, that too
at what type of relationship is it is.
Is This Answer Correct ? | 5 Yes | 1 No |
Explain the organizational structure of sap-ps module. List the parameters of project system.
Forming a team, developing the team and improving knowledge are direct responsibilities of the project manager, do you agree?
What are the parameters of project system?
What is the primary purpose of procurement management plan?
What is the role of isikawa/ fishbone diagrams in determining root causes of risks?
Can any one describe PS and other module integration? How can we do integration between PS-FI, PS-CO, PS-SD, PS-MM,PS-PM, PS-P2P etc. with details in configuration also?
What is unit costing?
How do you define a milestone?
For raising client billing, is there any possibility of linking line items in sd module with activities / wbs in ps module?
explain project planning board
Are there distinct kinds of activities in a project?
What are the ways a project time schedule can be compressed?