Answer Posted / subhrajyoti bhattacharjee
Relationship basically denotes how activities in a
networkorder are related to each other.They can be
classified into 4 categories - SS (Start-Start), SF(Start-
Finish), FF (Finish-Finish), FS (Finish - Start).
For 2 activities say A and B
SS -->> Both A and B start together
SF -->> Start of A coincides with finish of B and so on.
We can also specify the time gap between which these
relationships work. Say in an SS relationship, there can be
a 10 minutes gap between start of A and B and so on.
Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
Is there any way by which we can stop the network from attaching further materials after it is released?
Can you explain project life cycle?
What do ntw mean?
What is project definition?
How do you estimate in the three point estimating method?
Can anyone post the SAP-Project systems interview questions.
Explain time profiles.
explain settlement rules
What is standard project structure?
What is the role of isikawa/ fishbone diagrams in determining root causes of risks?
What is work breakdown structure (wbd) and how does it affect the work estimates of tasks/activities?
What are the important processes for project integration management?
What is the impact of coding mask on the project and where is it created (menu path) ?
What does procurement administrator involve?
How do you determine the communication needs of stakeholders?