how to estimate shuttering form work or how to take off material quantity???
Answers were Sorted based on User's Feedback
Answer / bharat raygor
shuttering area : perimeter length*height
| Is This Answer Correct ? | 1 Yes | 1 No |
to estimate shuttering form work for 1 cum of concrete 5 to 6 sqm of shuttering material required, calculate the concrete in cubic meter than multiply by 5.5 .
| Is This Answer Correct ? | 0 Yes | 2 No |
Answer / prem
work out for RCC quantity in cu.m .multipy that figure with 4 . you get shuttering quantity
| Is This Answer Correct ? | 1 Yes | 4 No |
how many 1st class bricks in 1cu feet?
28 Answers ECCI, Jayant Group, L&T,
For Beam steel reinforcement detailing, in the End of the beam do the making of L shape in the rebar is essential in all the cases, specially in the ends of the Beam?
Onsite percentage wastage of Concrete, Rebar, Blockwork/Brickwork, Plaster, Floor tiles ??
what is Bearing Capacity,How to determine it?
what is the difference between pumpable concrete and non pumpable concrete
What are new methods /technologies of pothole patching?
22. Are you willing to attend trainings, learn new skills and develop as a professional?
how meny typs of renging rod?
size of the traditional brick is 248*121*71 in mm,but why the size are like this.why the size are not like that 211*154*75 in mm
at what pressure ply-wood is obtained by gluing wooden sheets
What is binding spacing of the rebars at lapping zones.
12mm diameter iron bar having 1m length how much kg weighted ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)