how to estimate shuttering form work or how to take off material quantity???

Answers were Sorted based on User's Feedback



how to estimate shuttering form work or how to take off material quantity???..

Answer / bharat raygor

shuttering area : perimeter length*height

Is This Answer Correct ?    1 Yes 1 No

how to estimate shuttering form work or how to take off material quantity???..

Answer / honnikery-007

to estimate shuttering form work for 1 cum of concrete 5 to 6 sqm of shuttering material required, calculate the concrete in cubic meter than multiply by 5.5 .

Is This Answer Correct ?    0 Yes 2 No

how to estimate shuttering form work or how to take off material quantity???..

Answer / prem

work out for RCC quantity in cu.m .multipy that figure with 4 . you get shuttering quantity

Is This Answer Correct ?    1 Yes 4 No

Post New Answer

More Civil Engineering Interview Questions

what is the mean of opc cement and conceret grade 53 n?please explane with detail>

9 Answers  


Method of findingthe dry ingredient quantity of 1 m3 concrete. what is the difference between static and dynamic induced emf? Testing charges bill given for Rs. 32,000/- but not added service tax in this bill. So, How much TDS will be deduct

0 Answers   Suraj Constructions,


if column length is 12'(feet) then how to take ring bar on it?

2 Answers   AGI Infra, SIPL,


What is the difference between 53 grade and 43 grade cement

0 Answers   RPP Infra Projects,


Could you please give me an answer to the mixing proportion of concrete M1 grade (sterngth of 1 MPa)?

0 Answers   L&T,






what is the formula to calculate isolated footing

11 Answers   Supertech,


what is the price of a cubic meter of concrete on international market?

0 Answers  


Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?

0 Answers   L&T,


what is labour consume factor in residential projects

0 Answers  


sir my site not availabele 12mm steel now if i use 10 mm how many spacing require for slab design slab thk 200mm footing, column,raft,wall how can calculate give me formula

2 Answers   Amrapali,


How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure

0 Answers   Ravi Group,


which tests for concrete pouring period at the site?

5 Answers   Al Turki, L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)