How to calculate cement quantity in m20 concrete
Answer Posted / jayaprakashsst
M20 concrete means 1:1.5:3
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 bags
| Is This Answer Correct ? | 14 Yes | 1 No |
Post New Answer View All Answers
about higyway engineering
How will drive weight formula for circular cylinder steel bar in kg/ m please step by step drive?
we have a crushing plant and our product is experiencing flakiness and elongation over limit for granite. what is the solution to this problem? how can it be avoided and what to do differently? It is not ok for batching plants
how i convert mm into standard wire guage (SWG)no.
What goals do you have in your career?
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
crank types
What is the zero value in quantity surveying
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
How to come 1.54 from dry to wet concrete?
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
Coverage of 25mm.thick ratio of 1:4 cement mortar?
How to find CN by using arcgis 9.3?
what isload waring calculation
What is the Maximum %age of Steel in columns and beams ?