How to calculate cement quantity in m20 concrete
Answer Posted / jayaprakashsst
calculation of cement quantity in m20 concrete
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 kgs
| Is This Answer Correct ? | 4 Yes | 2 No |
Post New Answer View All Answers
what is the effect of duration of earth quake on framed structures ?
sir iam dng my engg final yr (civil) iam intrested to write group_1 .if we write this exam what kind of jobs we get and what should be the minimum score for us to get qualified and iam having reservation too.
What are the Types Of DPC and its Thickness used?
1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall
what is meant by shear center?????
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.
Discuss some applications of modular elasticity?
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
how to calculate the density for high density concrete ? or is it same as the density of RC?
how i can tak Quantity of mortar in block work
acceptance criteria for concrete works
In Abutment walls (A1 side) why we are adopting fixed bearing (POT-PTFE)?
what r you reqired for concrete baching plant?
What are the methods of measurement? Describe it shortly
How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.