How to calculate cement quantity in m20 concrete
Answer Posted / jayaprakashsst
calculation of cement quantity in m20 concrete
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 kgs
| Is This Answer Correct ? | 4 Yes | 2 No |
Post New Answer View All Answers
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
What you understand by richter scale?
Calculation of curtain wall of box culvert
what do you understand by M25 concrete
What is Time period of a building and its relation with frequency ?
How can we convert weight batch to volume batch for m30 mix
how many kg cement & fine sand reqird in one sq meter 1:6 mortar ratio?
sir, whitch is the best book (writer name) for prepration of gate....
how to convert cement, sand aggregate quantity from M3 to kg with full description?
For what purpose bedding is used under storm water drains, explain?
What is Gsb tollens ?
What is the use of extend command?
What is the difference between 53 grade and 43 grade cement
How to calculate the cement plastering for circular and rectangular water storage tanks and how to calculate the area of circular and rectangular floor?? Please help me