if we get water mor from 28 days to the rcc concret is this better or have a damag
Answers were Sorted based on User's Feedback
Answer / santosh
as we know after 28 days concrete attains 90% of its strength
and concrete takes years to attain 100% of its strength so there is no point curing more.it is wastage of water
Is This Answer Correct ? | 15 Yes | 0 No |
how to calculate the quantity of material in 1 cubic meter Concrete?
what is the most suitable foundation when construct a bird watching tower in a marshy land
How could I calculate quantities of fine aggrigates(sand) & coarse aggregates in pcc M15
1 Answers Coromandel, RECPDCL,
sir tell me what are the rules to find out the cut length? and what is the deduction in dia to be made ?
What is the strength of concrete with ratio 1:4:8 as per British standard or ACI
Where are laterally loaded piles are used in practice?
What you understand by building codes?
what is tmc ,term is used in measureing water, pls tell me 1 tmc = how many litres?
18 Answers College School Exams Tests, Irrigation, IT Consulting Services, IVRCL,
While calculating quantity of cement required for 1 qubic meter If mix is m25 1:1:2 =4 1.52/4=0.38, 0.38x1440=547.20 kgs I know 1440 is unit weight of cement And what is 1.52 ? And some one using 1.54 and 1.53 etc... Why they are using can u explain me what is 1.52, 1.53, 1.54?
HOW WE WILL CALCULATE QTY. OF CEMENT,SAND & AGGREGATE (10MM&20MM) IN Kg.
4 Answers Nagarjuna Construction,
which steel is better for residential building tmt steel or hysd steel
What is the different type of slump test indications?