Answer / santhoshselvamani
pre stressing means before concrete we was stressing the
cable(tendons)
post tensioning means afterporing the concrete we will
stressing the tentons,
pretension mainly usedfor bridges
post tension mainly used for buildings
Is This Answer Correct ? | 14 Yes | 6 No |
Answer / ashok reddy
Prestressing carried out prior concreting.
Post tensioning carried out once the 7 days cube testing is done.
Is This Answer Correct ? | 0 Yes | 0 No |
Dfine superelevation.it depends upon which of the following. 1.surface condition of road 2.width of road 3.radius of curve 4.speed of vehicle
What is the strength of normal brick in india
how to design a formwork for beam, how to determine the load baring capacity of the cuplock system and which is the relevant code for the same.
Why we used ther red bricks for construction..
what is diff between auto level and dumpy level?
What is meaning of FREE STANDING STAIRCASE ?
What is the diffence between prescribed mix and design mix
How to Calculate steel
Minimum spacing of 2- bars in column, beam, slab
where we provide hinged joint in a framee structure ?
what is 43 and 53 grade of cement? that 43 & 53 represents what?
1:6 brick masonry cement and sand calculations