Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


calculate if the size of the beam is 300*500 then L for the top & bottom bar

Answers were Sorted based on User's Feedback



calculate if the size of the beam is 300*500 then L for the top & bottom bar..

Answer / sreekumar

if the cover is 30mm each L = 440mm

Is This Answer Correct ?    2 Yes 1 No

calculate if the size of the beam is 300*500 then L for the top & bottom bar..

Answer / vijay

ans. is 425 but how explain it..

Is This Answer Correct ?    1 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

In case of a beam ,main steel is provided along the longer span because, bending moment is directly proportional to length but why in case of one way slab main steel is provided along shorter span while as bending takes place along longer span?comment

8 Answers   Power Grid,


WHAT WII BE THE WATER ABSORPTION POWER OF WOOD ?

0 Answers  


Explain the mechanism of cavitations in pipes and drains?

0 Answers  


WHAT IS YOUR FUTURE PLANS FOR THE COMPANY IF PERMANENTLY EMPLOYED

4 Answers   Oil and Gas Jobs,


what is the meaning of morth

1 Answers   L&T, Maytas,


How do we calculate the building footing calculation ?

7 Answers   Dodsal, L&T,


Describe the various methods of concrete curing?

0 Answers  


why steel is used in rcc columns? what is its purpose?

3 Answers  


1M2=how much M3?

7 Answers  


How you can turn off the display for dimension in CAD?

0 Answers  


please send me bhel questions on rupesh.017@rediffmail.com

0 Answers   Bhel,


As shown in IS 456-2000 minimum cement content is include fly ash?

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)