calculate if the size of the beam is 300*500 then L for the top & bottom bar
Answer Posted / sreekumar
if the cover is 30mm each L = 440mm
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com
how to convert cement, sand aggregate quantity from M3 to kg with full description?
How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated
how to caluclate sienerge qty in construction in ap
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
how find the cut length of tringular ring and any formula find out the quantity of circular brick work
Which tests are performed on soil to decide the type of foundation to be provided.
what course did you consider thinking before you enrolled in college?
Which are the top apps for you civil engineering?
How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
What will you do if a portion of load bearing wall collapses under your supervision?
what is called Bulk Density of aggregate?
How much quantity of cement,sand,stone used to build 1 cum of cc road??