FOR M20 grade of concrete the ratio is 1:1.5:3 or 1:1/2:3
Cement = 15.4/(1+1.5+3) = 2.8 cum
i.e. Cement = 2.8/ 0.0347 = 80.7 kgs
where, 0.0347=50/1440 One bag of cement (50kg) & 1cum weight oof Ordinary Portand Cement = 1440kg
Fine Aggregate=2.8*1.5=4.2cum
Coarse Aggregate=2.8*3=8.4cum
| Is This Answer Correct ? | 1 Yes | 0 No |
kindly tell me name of a book to calculate bbs?
24. Why should we hire you?
which is the cheapest type of flooring (say for using for 6 months in a factory building & dismantling it)?
how to carry out rate analysis for RCC work in column using M20 ?
1 Answers Mazna Building Contracting,
How to do rate analysis for concrete work including shuttering work?
0 Answers DBM, Techno Solutions,
limit value of bulking of sand
13. What are your expectations from this possible relocation to our company?
where is dolpin pile is used
3 Answers IGCAR, Sekar Construction, Soba,
how much to get of BRC lapping in full yield and half yield ?
For M25 concrete ,what is the maximum compressive strength at 28 days ?
6 Answers L&T, Techno Builders,
How will drive weight formula for circular cylinder steel bar in kg/ m please step by step drive?
can any one tell me in detail footing estimation .. i am new here in dubai so facing lots of problem...
0 Answers Golden Bridge Contracting,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)