Answer / ajay saini
for M-30 Mix design in zone 2 the w/c ratio is 0.45 so the consumption of cement is 425 kg/cum.water 169 kg,10mm 523 kg,20mm 784 kg, sand 541 kg, admixture 200 gm/bag
| Is This Answer Correct ? | 2 Yes | 1 No |
How do you change a dimension value in solidsworks?
why we use min. 12mm dia bar in a coloum.
7 Answers BPCL Bharat Petroleum,
How to find the concrete volume in sloped footing??? illustrate with example
As column is compression member then why we use steel to make it reinforced as it is already capable of taking compressive load?
2 Answers MBL Infrastructures,
What is M40 _ TOR - EQ and B.F.S
0 Answers Odisha Hydro Power Corporation, Ramky, Simplex,
what is the full form of GGBS?
What are the advantages of Prestressed Concrete
how can i calculate pcc and rcc cu.mtr rate? specify labor and material cost should be diff
what is the difference between highway and motorway?
cement and sand required for one block of size 0.23*0.15*0.46
what"s the different between OPC (ordinary portland cement) and PPC (pozalana portland cement)?
3 Answers Ashok Leyland, Marathon Realty,
we are provide groove at sides of door & window frames, columns & beams any water dampness & seepage in external side? explain it
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)