Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is the stripping time of beam column & slab?

Answers were Sorted based on User's Feedback



what is the stripping time of beam column & slab?..

Answer / karunakaran

For Beams sides only 1 day
For coloumns 1 day
For slabs span<4.50m 7 days
For slabs span>4.50m 14 days

Is This Answer Correct ?    14 Yes 0 No

what is the stripping time of beam column & slab?..

Answer / sjtbehera

14days

Is This Answer Correct ?    5 Yes 12 No

Post New Answer

More Civil Engineering Interview Questions

Hi frens, i need MahaGenco previous exam papers of civil engineering as well recent MahaTransco exam papers? If anybody having it plz help or at least i want to know which subject shuold i focus for studies? Thanks in advance.

0 Answers  


What are the composition of a landfill?

0 Answers  


what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?

0 Answers  


calculate 1-2-4 ration concrete - cement - sand metal and water required for 1 cum

4 Answers   Gresp, L&T,


How to find the requirement of cement and sand for the 1cum of rr masonry work

1 Answers   S Tech,


Define What is the force exerted by the Tacoma narrows bridge?

0 Answers  


How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?

0 Answers   KD infra,


1)define the critical items in rcc framed G+18 bldg. as Cr Activity 1,Cr Activity 2,Cr Activity 3...etc. 2)on what logic is MSP and Primavera planning based.FS SF FF...

2 Answers  


Plan and schedule for 14 towers of 6 floors each with 6 flats on each floor?

1 Answers   L&T,


How many cum of 9.5mm stone in 1 ton ?

0 Answers   GT Realty,


what is mean civil

5 Answers  


what is density on steel bars?

3 Answers   AICL,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)