what is the stripping time of beam column & slab?
Answers were Sorted based on User's Feedback
For Beams sides only 1 day
For coloumns 1 day
For slabs span<4.50m 7 days
For slabs span>4.50m 14 days
| Is This Answer Correct ? | 14 Yes | 0 No |
how to replace 8mm bar with 10mm bar if the the 8mm bar is not available..???
At which place Construction joint should provide in slab and Beam at the time of casting.
If specific gravity of cement is less than 3.15 what is the cause?
How can we make a hole in a solid rectangle using solidsworks?
For M30 grade how much cement bags will need for one cubic meter qty
Calculate the maximum allowable speed on a horizontal curve of radius 350m if the maximum allowable values of the lateral coefficient of friction are 0.14 and the rate of superelevation is 0.08.
The effect of arching the beam is?
what is the mean of opc cement and conceret grade 53 n?please explane with detail>
what is diffence in grade 43 & 53 of cement?
4 Answers KFC, L&T, NICE, Puravankara,
Why use of fly ash in cement
How to estabilish reinforcement Steel rolling margin for a building projects ?
How to calculate shuttering plate weight
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)