For Beams sides only 1 day
For coloumns 1 day
For slabs span<4.50m 7 days
For slabs span>4.50m 14 days
| Is This Answer Correct ? | 14 Yes | 0 No |
how much quantity of mortar required for cement pointing work?
0 Answers City Corporation, Pragya Construction, Simplex,
plz.show development and anchorage length in simple diagram.
What is the difference between pvc,cpvc and upvc and where it is used as per their properties?????
convert 1 kilo into brass
wat is the size of fine aggregate & coarse aggregate?
How to calculate plastering for elevated water storage tank
what is pile cap and why its used ??? why its provided in different shape
what is the difference between pumpable concrete and non pumpable concrete
How foundation is designed, Column design and beam design
What are the precautions needs during concrete pouring in very hot weather?
What is an inverted beam??
Define what is quality...
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)