how to calculate the weight of bending wire for 1sqmts .how
much bending use for 1ton steel

Answers were Sorted based on User's Feedback



how to calculate the weight of bending wire for 1sqmts .how much bending use for 1ton steel..

Answer / sjtbehera

For 1 tone steel it is around 8 to 10 kg

Is This Answer Correct ?    16 Yes 0 No

how to calculate the weight of bending wire for 1sqmts .how much bending use for 1ton steel..

Answer / shyam ji maurya lnt sr.enginee

BINDING WIRE USED AS PER REINFORCEMENT DIA.NORMALY 10 TO 12 KG PER TON USED AT SITE INCLUDING WASTAGE.

Is This Answer Correct ?    5 Yes 0 No

how to calculate the weight of bending wire for 1sqmts .how much bending use for 1ton steel..

Answer / vinod

Approximately 8 to 10 kg.
It depends on-
The type of Structure mostly.
And Dia. of Bar too.

Is This Answer Correct ?    2 Yes 0 No

how to calculate the weight of bending wire for 1sqmts .how much bending use for 1ton steel..

Answer / ravindrarana8421

Binding Wire = 8kg/ton

Is This Answer Correct ?    2 Yes 0 No

how to calculate the weight of bending wire for 1sqmts .how much bending use for 1ton steel..

Answer / nareneder kumar

pending wire 10kg/ton

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

What is diversion tunnel in a dam?

0 Answers  


How many cement sand ballast in cc 1:4:8 40mm

0 Answers  


what is the difference between rise and tread? what is its standered size? what is waist slab?what is the standered length of staire-case? also what is the angle between floor and landing?

5 Answers  


Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?

0 Answers  


while measuring slab for concrete Quantity it is practiced that steel quantity is not deducted in that particular qty.why?

0 Answers  






What letter follows after these, O, T, T, F, F, S, S, E, __?

2 Answers   Alstom,


. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.

0 Answers  


What is the diff between cad & cadd?

0 Answers  


how we control the temperature during concreting ?

4 Answers  


What is unit weight of roadway layer.. 1.bitumen 2.sand 3.soil 4.concrete 5. aggregate give me some reference for this answers

0 Answers  


for columns reinforcement the lap length is not provided then how to rebar the rods then how rebar should be lapped

4 Answers   Nagarjuna Construction,


Rate of plasting per sq.ft...?

4 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)