what is the initial setting time & maximum duration concrete
get hardening for ordinary portland cement?
Answers were Sorted based on User's Feedback
Answer / karthik rajendren
The initial seting time for OPC is 30 mins and max time 10
hrs to become hard.
| Is This Answer Correct ? | 24 Yes | 3 No |
Answer / sabari
The initial setting time of the cement should not be less
then 30mins,final setting time of the cement should not be
more than 10hrs
| Is This Answer Correct ? | 10 Yes | 2 No |
Answer / ajaybir
initial setting time = 30 min
Maximum setting time = 600 minutes
| Is This Answer Correct ? | 7 Yes | 0 No |
how many cubic feet in one unit of sand?
16 Answers L&T, PSPCL, Ratna Infrastructure Projects,
What is the meaning of Fe415 ?
6 Answers Arul Constructions, L&T, SSM,
What is progress payment?
how can change 12mmdia@150c/c bar spacing to 16mmdia
12 Answers Amanah Tech, Envoy Group, Globus Constructions,
which steel is better for residential building tmt steel or hysd steel
What is meant by Anchorage length? Development Length?
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal
what is the ratio of cement water and sand in RCC?
what is the difference between ribbed steel & tor Steel ?
In IS:456-2000 the workability of concrete is given in mm (slump)in cl.7.1. In IS:10262-1982, cl.3.3.4 & table-6 says +/- 3 percent adjustment is required in the quantity of water (calculated as per table-4 or 5), for each increase or decrease in the value of compacting factor (i.e. workability of concrete) by 0.1. How it is possible to calculate the exact quantity of water required for a particular grade of concrete? What is the relation between Slump & Compacting factor of concrete?
curing of concrete why 7day's,14day's 21day's 28days
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)