how can change 10mm dia @275 c/c bar spacing to 12 mm

Answers were Sorted based on User's Feedback



how can change 10mm dia @275 c/c bar spacing to 12 mm..

Answer / soham manna

400mm

144/100*275=396mm or 400mm

Is This Answer Correct ?    10 Yes 3 No

how can change 10mm dia @275 c/c bar spacing to 12 mm..

Answer / anusha

Spacing is directly proportional to square of diameter, so
X/275 = 12^2/10^2
X= 396 mm c/c
as per IS 456:2000, spacing should not be greater than 300mm
X = 300 mm

Is This Answer Correct ?    6 Yes 1 No

how can change 10mm dia @275 c/c bar spacing to 12 mm..

Answer / s k majumder

10/275 = 12/x



x= 330 mm

As dia increase spacing will be increase. however better to spacing limited to 300mm

Is This Answer Correct ?    6 Yes 4 No

how can change 10mm dia @275 c/c bar spacing to 12 mm..

Answer / anandbala

12 MM

Is This Answer Correct ?    1 Yes 4 No

Post New Answer

More Civil Engineering Interview Questions

how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?

0 Answers  


what is civil engineer greatest strength and weakness?

0 Answers   Cube, NCC,


what is the load bearing capacity of the scafolding pipe (50mm) and other.

3 Answers   Gammon, IVRCL, L&T,


In the cement the compound quickest to react with water

2 Answers  


form work including the props can be removed from beams only after

1 Answers  






What is Pavement & carrage way?

7 Answers   NBCC,


what is a coupler and where do u use it ?

1 Answers   ITC Infotech,


can any1 mail me IS CODES and quality check sheet of materials..? its urgent plz

3 Answers  


What is the per cu. mt. price of ready mix in Gujarat region.?

0 Answers   Neptune,


How calculate the physical stock of material such as Fine/Coarse aggregate,sand & stone dust laying at site?

3 Answers  


if rise and tread of stairs rae 16 & 25cm with landing slab of thickness 100mm . If there are 8steps, and carpenter ask for to mark the bottom of centering of landing on column, what will be the height above floor finished level?

2 Answers  


What is approximate % of wastage considered for Marble and vitrified tiling works (flooring)?

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)