what is the initial setting time & maximum duration concrete
get hardening for ordinary portland cement?
Answer Posted / sabari
The initial setting time of the cement should not be less
then 30mins,final setting time of the cement should not be
more than 10hrs
| Is This Answer Correct ? | 10 Yes | 2 No |
Post New Answer View All Answers
how water proof chemicals act in concrete to avoid leek?
what is the cost of rcc roof casting of 400 sq. ft. in kolkata
what would be the design load of R.C.C Cooling tower per cell.?
how gradation of aggregates effect on slump of fresh concrete?
Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..
Which are the Steel tests ?
how many digree of freedom in four bar chain
what discoveries did you have in relation to your course?
what is diversion?
Explain what is change order request?
When was the first motorway built in england?
Explain creep?
What is the meaning of Brick- M 35 grade? Is it a common brick or it's a concrete brick?
What is difference between code and standard and specification?
What materials were used to build the golden gate bridge?