Brick size 230X115X150mm, how many bricks, quantity of sand,
cement required to construct 10 sq mtrs of 115mm thick brick
wall.
Answers were Sorted based on User's Feedback
Answer / sha
Consider 1 cm mortar..
so the size is .24 x .16=0.0384
num of bricks is=10/0.0384=260 nos
| Is This Answer Correct ? | 7 Yes | 4 No |
Answer / nirmala
earthwork excavation by manual means for foundation of buildings,culverts,water supply and sanitary lines and electrical conduits etc.either in pits or in trenches, in ordinary soil including dressing the bottom and sides of pits and trenches,stacking the excavated soil clear from edges of excavation with lead up to 50m,including breaking of clods complete as per specification ,including pumping of water,including cost of all labour,material,transport,hom of machineries,all lifts,loding and unloding .specification no KBS 2.1(a)/2.3.5.work to be completed as per the directions of the engineer in charge.
UNIT QUANTITY RATE(IN RS) AMOUNT(IN RS)
Cum 230 204 46920
please tell me the how its came quantity
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sjtbehera
Brick size- 230 x115x50Consider 10 sqm - 10x.115=1.15cum 115mm th.
Normally mortar joint will be less than 1cm, taking 1cm mortar joint the actual th. Of wall thickness will be-.105mm
So, actual volume- 10x.105=1.05 cum.
No. Of bricks= 1.05/.23*.115*.150=264 nos. Take 5% wastage it comes around 280 nos.
Mortar requirement- total volume of brickwork- 1.05 cum
For fog filling, for use of cut brickwork, uniform joints take 15% extra
So total volume- 1.05+1.05*15%=1.2075
For dry volume, volume increase 1/4 th ofmortar so 1.2075+1.2075/4=1.509 cum
So for 10 sqmt 1.509 cum mortar
If you take 1:6 then you calculated cement and sand
1.509/7=.215 cum
Sand=.215x76= 1.29 cum
| Is This Answer Correct ? | 6 Yes | 17 No |
if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?
how to distinguish TMT n Tor steel?
what is the design procedure for building
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.
How to find the concrete volume in sloped footing??? illustrate with example
What is a MIS report?
What is the lap lenth for welded joints for reinforcement bars. and what is its IS code no.
How much standard bricks required for a wall of 9*1200*1200 inches
What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.
Why was the empire state building made of steel?
what is the constant weight of the 6mm,8mm,10mm,12mm,20mm,25mm etc.............dia bars in 1meter
how to prepare analysis of hire charges for 62.5 KVA generator
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)