Brick size 230X115X150mm, how many bricks, quantity of sand,
cement required to construct 10 sq mtrs of 115mm thick brick
wall.

Answers were Sorted based on User's Feedback



Brick size 230X115X150mm, how many bricks, quantity of sand, cement required to construct 10 sq mt..

Answer / sha

Consider 1 cm mortar..

so the size is .24 x .16=0.0384

num of bricks is=10/0.0384=260 nos

Is This Answer Correct ?    7 Yes 4 No

Brick size 230X115X150mm, how many bricks, quantity of sand, cement required to construct 10 sq mt..

Answer / nirmala

earthwork excavation by manual means for foundation of buildings,culverts,water supply and sanitary lines and electrical conduits etc.either in pits or in trenches, in ordinary soil including dressing the bottom and sides of pits and trenches,stacking the excavated soil clear from edges of excavation with lead up to 50m,including breaking of clods complete as per specification ,including pumping of water,including cost of all labour,material,transport,hom of machineries,all lifts,loding and unloding .specification no KBS 2.1(a)/2.3.5.work to be completed as per the directions of the engineer in charge.
UNIT QUANTITY RATE(IN RS) AMOUNT(IN RS)
Cum 230 204 46920


please tell me the how its came quantity

Is This Answer Correct ?    0 Yes 0 No

Brick size 230X115X150mm, how many bricks, quantity of sand, cement required to construct 10 sq mt..

Answer / sjtbehera

Brick size- 230 x115x50Consider 10 sqm - 10x.115=1.15cum 115mm th.

Normally mortar joint will be less than 1cm, taking 1cm mortar joint the actual th. Of wall thickness will be-.105mm
So, actual volume- 10x.105=1.05 cum.

No. Of bricks= 1.05/.23*.115*.150=264 nos. Take 5% wastage it comes around 280 nos.

Mortar requirement- total volume of brickwork- 1.05 cum
For fog filling, for use of cut brickwork, uniform joints take 15% extra
So total volume- 1.05+1.05*15%=1.2075

For dry volume, volume increase 1/4 th ofmortar so 1.2075+1.2075/4=1.509 cum
So for 10 sqmt 1.509 cum mortar

If you take 1:6 then you calculated cement and sand
1.509/7=.215 cum
Sand=.215x76= 1.29 cum

Is This Answer Correct ?    6 Yes 17 No

Post New Answer

More Civil Engineering Interview Questions

How to hide dimensions in autocad?

0 Answers  


what is formwork in construction

4 Answers  


how many liters of water required for 1cu.m concrete?

3 Answers  


Is there any codal provision stating the actual diameter for chair bars?

1 Answers   CADS Software,


List out some of the software used in the construction sector to estimate cost and monitoring expenses?

0 Answers  






how to calculate the steel quantity for columns and beams

7 Answers   CMR,


curing of concrete why 7day's,14day's 21day's 28days

5 Answers   Gammon,


it is a corrected question." make a list of engineering property(properties) of soil.

0 Answers   AAI Airports Authority Of India, DLF,


What are the functions of a column in a building?

1 Answers  


how many spacers we need for 1 ton reinforcement? aprox.

0 Answers   ACC, J&P, LST,


What is the largest concrete dam in the world?

0 Answers  


What is the specific weight of sand?

14 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)