Brick size 230X115X150mm, how many bricks, quantity of sand,
cement required to construct 10 sq mtrs of 115mm thick brick
wall.
Answer Posted / sjtbehera
Brick size- 230 x115x50Consider 10 sqm - 10x.115=1.15cum 115mm th.
Normally mortar joint will be less than 1cm, taking 1cm mortar joint the actual th. Of wall thickness will be-.105mm
So, actual volume- 10x.105=1.05 cum.
No. Of bricks= 1.05/.23*.115*.150=264 nos. Take 5% wastage it comes around 280 nos.
Mortar requirement- total volume of brickwork- 1.05 cum
For fog filling, for use of cut brickwork, uniform joints take 15% extra
So total volume- 1.05+1.05*15%=1.2075
For dry volume, volume increase 1/4 th ofmortar so 1.2075+1.2075/4=1.509 cum
So for 10 sqmt 1.509 cum mortar
If you take 1:6 then you calculated cement and sand
1.509/7=.215 cum
Sand=.215x76= 1.29 cum
| Is This Answer Correct ? | 6 Yes | 17 No |
Post New Answer View All Answers
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?
Explain what is 1/8 on the architect ruler denotes?
types of piles detail,
how can we calculate steel value, depending on load
manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
How high should the water tank be to provide a 60 psi at base of this water tower?
what is the composition of good brick ?
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.
what is Quantity of stone and sand required for one cubic meter of stone work (UCR)
Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.
What in your past experience or education prepares you for the position for which you are applying
foundation details for 25 ton weight Furnace on 2 supports and 2 tilters
What is made from large rocks, which protects the base of cliffs?
What is progress payment?