L&T ACB C-POWER OF 800A FAULS TRIPING AT THE TIME OF 110KW
MOTOR STARTS WITH EARTH FAULT RELEASE
If it is new and under test ,CT might have been provided on
neutral instead of phase.If not , mostly due to pole
discrimination ( all poles not closing simultaneously ).
Disable instant element while closing .
| Is This Answer Correct ? | 0 Yes | 0 No |
how much current and power in watts can be carry by 2.5^2mm cu wire and 4 core 10^2mm Al cable?
why supervision relay is used in incoming feeders?
i applied for the ap transco please forward the freqventley asked QA
What is the electrical difference between Earthing Switch (ES) and Maintenance Earthing Switch (MES)?
what is the last range of mccb in amp?
how much load should be given on 5 mva transformer
7 Answers NTPC, OHPC, Power Grid,
How many earthing pits required for diesel generator set ? Why ?
I want to merge a cable..in between two metering Cubicals which contains CT's and PT's and Energy meter..before taking merger..what are the common things required?
I want to do a mini project. Now I'm studying in 6th semis tor EEE Engineering.
why earth hole size is biggest in plug point?
How is the air circuit breaker quenching the arc. If it is by air means, where is it come from?
how do i convert 22kw to kva
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)