Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


What is the cement and sand consuption of 1:4 block work

Answers were Sorted based on User's Feedback



What is the cement and sand consuption of 1:4 block work..

Answer / rakesh

cement part = 1/5, sand part = 4/5
now 1m3 of cement weighs 1440 kg and cube contains only 1/5part of it as cement. therefore, 1/5* 1440 kg cement present . and rest as sand..i.e. 1440*4/5kg

Is This Answer Correct ?    3 Yes 0 No

What is the cement and sand consuption of 1:4 block work..

Answer / abdul rasheeth

cement &sand ratio is 1:4
i.e.,1 ratio cement for 4 ratio of sand
cement quantity for this ratio =ratio of cement/ratio of sand
=1/4=0.25 ratio cement
we know that 1 m^3 cement =1440 kg
therefore amount of cement =0.25*1440 = 360 kg/m^3
lly the amount of sand is =360*4 =1440 kg/m^3

Is This Answer Correct ?    6 Yes 4 No

Post New Answer

More Civil Engineering Interview Questions

what is the difference between arch dam and gravity dam. Name a gravity dam in India

6 Answers   AAI Airports Authority Of India, L&T,


why we providing 40mm cover to columns & 25mm to shear wall

1 Answers   NCC,


9*9 1:4:8 ratio using for p cc work please tell quantity 40mm aggregate ,sand &cement

8 Answers   L&T,


What are the tests on concrete?

1 Answers  


Why there is no use of sea water in producing electricity

20 Answers   Infosys,


how to calculate the steel quantity for columns and beams

7 Answers   CMR,


Is there any software to prepare the Estimate of building.Plz tell me.......

10 Answers   L&T,


what is shuttering co efficient?

0 Answers  


how calculate cutting length of stell in slab and column? give brif discussion with formula?

3 Answers   ATS, Gammon, Pegasus,


what affect on the structure and related beam of slab when provide one way slab insteade of two way slab

2 Answers  


How many Sqm can laid Vitrified tiles for flooring per day per masan?

2 Answers   L&T,


What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?

0 Answers   gdcl,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)