What is the cement and sand consuption of 1:4 block work
Answer Posted / abdul rasheeth
cement &sand ratio is 1:4
i.e.,1 ratio cement for 4 ratio of sand
cement quantity for this ratio =ratio of cement/ratio of sand
=1/4=0.25 ratio cement
we know that 1 m^3 cement =1440 kg
therefore amount of cement =0.25*1440 = 360 kg/m^3
lly the amount of sand is =360*4 =1440 kg/m^3
| Is This Answer Correct ? | 6 Yes | 4 No |
Post New Answer View All Answers
What is a kip?
How much cement and water required for cement selery????
how to calculate the strength of rebound hammer test reading in building construction ?
rcc floor to floor 4m. in column reinforcement where we provide lap in exact location.
construction workers how much time take one work or qty
what is idealized curve for concrere and steel
What is the yield of 100 litres of water and 10 kg of cement in grout mix?
what is labour consume factor in residential projects
how i can tak Quantity of mortar in block work
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter
what is work of planning deptt. in any construction compny (in road project)
pls tell me , what is the water content
What is costing in 100squre feet bricks
according to the painting co efficient, we should take the one side of doors (or) windows or both sides?
HOw much % of premium on DSR-2013 currently