What is the cement and sand consuption of 1:4 block work
Answer Posted / abdul rasheeth
cement &sand ratio is 1:4
i.e.,1 ratio cement for 4 ratio of sand
cement quantity for this ratio =ratio of cement/ratio of sand
=1/4=0.25 ratio cement
we know that 1 m^3 cement =1440 kg
therefore amount of cement =0.25*1440 = 360 kg/m^3
lly the amount of sand is =360*4 =1440 kg/m^3
| Is This Answer Correct ? | 6 Yes | 4 No |
Post New Answer View All Answers
What is the use of array command?
What is difference between code and standard and specification?
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
can i make bricks using M10 grade concrete ? and what would be the cost of a brick if we use m10 grade concrete sand and aggregates ??
Explain the different types of building contracts?
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
Why Vitrified tile are getting pop up.
Explain what is Hybrid Foundation?
is concealed wiring a problem in fly ash brick wall?
What is the difference between yeild strength and compressive strength of steel???
What is Gsb tollens ?
What are the types of slump?
as per is code, what is the minimum content of opc and ppc cement for rcc structure
give me the rate analysis for Bituminous Macadam and SDBC